Assessment Year | 1997 |
---|---|
Principal Product | pipeline maintanance equipment |
NAICS |
n/a
|
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
125,000
ft2
|
Annual Production | 35,014,000
lb
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,530 | 3,778,429 |
kWh
|
$0.026 |
Electricity Demand | $89,688 | 9,017 |
kW-mo/yr
|
$9.95 |
Electricity Fees | $876 | - |
|
- |
Natural Gas | $54,449 | 17,166 |
MMBtu
|
$3.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $72,463 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,195 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.4114: Replace city water with recycled water via cooling tower | $844 | $2,845 |
$(-159.0)
(-1,465)
kWh
|
- |
$1,003
-
Tgal
|
- | - | - | |
02 | 3.1191: Change procedures / equipment / operating conditions | $1,918 | $3,500 |
$(-57.0)
(-2,052)
kWh
|
- | - |
$2,695
-
lb
|
$(-720.0) | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $103 | $200 |
$203
7,034
kWh
|
- | - | - | $(-100.0) | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $(-70.0) | $386 |
$57
2,052
kWh
|
$26
-
kW-mo/yr
|
- | - | $(-153.0) | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $282 | $880 |
$282
9,672
kWh
|
- | - | - | - | - | |
06 | 3.5311: Recover and reuse waste material | $54,126 | $4,480 | - | - | - |
$(-558.0)
-
lb
|
- | $54,684 | |
07 | 3.5316: Contract a wood pallet recycling company | $198 | - | - | - | - |
$198
-
lb
|
- | - | |
08 | 4.452: Eliminate shift | $10,400 | $200 | - | - | - | - | $10,400 | - | |
09 | 2.3191: Use demand controller or load shedder | $4,662 | $15,500 | - |
$4,662
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $72,463 | $27,991 |
$326
15,241
kWh
|
$4,688
-
kW-mo/yr
|
$1,003
-
Tgal
|
$2,335
-
lb
|
$9,427 | $54,684 | ||
TOTAL IMPLEMENTED | $13,195 | $7,131 |
$44
5,569
kWh
|
$26
-
kW-mo/yr
|
$1,003
-
Tgal
|
$2,695
-
lb
|
$9,427 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs