ITAC Assessment: OK0350
ITAC logo
ITAC Assessment: OK0350
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product AIRCRAFT PARTS
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 850
Plant Area
n/a
Annual Production 1,265,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $703,199 14,726,260
kWh
Natural Gas $202,259 89,068
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,775 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7261: Install timers and/or thermostats $3,574 $1,300 - $3,574
-
MMBtu
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $9,981 $2,550 - $9,981
-
MMBtu
-
03 2.6232: Install set-back timers $162 $330 $162
4,689
kWh
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,525 $25,022 $8,525
241,794
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $16,499 $35,947 $16,499
313,599
kWh
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $914 - $1,064
30,188
kWh
- $(-150.0)
07 2.7142: Utilize higher efficiency lamps and/or ballasts $120 - $305
6,448
kWh
- $(-185.0)
TOTAL RECOMMENDED $39,775 $65,149 $26,555
596,718
kWh
$13,555
-
MMBtu
$(-335.0)
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs