| Assessment Year | 1991 |
|---|---|
| Principal Product | AIRCRAFT PARTS |
| NAICS |
n/a
|
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 850 |
| Plant Area |
n/a
|
| Annual Production | 1,265,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $703,199 | 14,726,260 |
kWh
|
$0.048 |
| Natural Gas | $202,259 | 89,068 |
MMBtu
|
$2.27 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $39,775 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $3,574 | $1,300 | - |
$3,574
-
MMBtu
|
- | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $9,981 | $2,550 | - |
$9,981
-
MMBtu
|
- | |
| 03 | 2.6232: Install set-back timers | $162 | $330 |
$162
4,689
kWh
|
- | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,525 | $25,022 |
$8,525
241,794
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,499 | $35,947 |
$16,499
313,599
kWh
|
- | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $914 | - |
$1,064
30,188
kWh
|
- | $(-150.0) | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $120 | - |
$305
6,448
kWh
|
- | $(-185.0) | |
| TOTAL RECOMMENDED | $39,775 | $65,149 |
$26,555
596,718
kWh
|
$13,555
-
MMBtu
|
$(-335.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs