Assessment Year | 1991 |
---|---|
Principal Product | REBUILT AIRCRAFT ENGINES |
NAICS |
n/a
|
SIC | 3724: Aircraft Engines and Engine Parts |
Sales Range | $1 M to 5M |
# of Employees | 40 |
Plant Area |
n/a
|
Annual Production | 300
pieces
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $14,508 | 237,691 |
kWh
|
$0.061 |
Natural Gas | $2,722 | 553 |
MMBtu
|
$4.92 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $3,346 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,346 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,200 | - |
$1,260
21,395
kWh
|
- | $(-60.0) | |
02 | 2.7261: Install timers and/or thermostats | $1,787 | $1,500 |
$812
9,672
kWh
|
$975
-
MMBtu
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $197 | $78 |
$197
3,224
kWh
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $162 | $395 |
$162
2,638
kWh
|
- | - | |
TOTAL RECOMMENDED | $3,346 | $1,973 |
$2,431
36,929
kWh
|
$975
-
MMBtu
|
$(-60.0) | ||
TOTAL IMPLEMENTED | $3,346 | $1,973 |
$2,431
36,929
kWh
|
$975
-
MMBtu
|
$(-60.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs