Assessment Year | 1985 |
---|---|
Principal Product | CUSTOM MOLDED RUBBER & PLASTIC |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
n/a
|
Annual Production | 650,000
pieces
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $221,320 | 4,327,081 |
kWh
|
$0.051 |
Natural Gas | $137,793 | 37,632 |
MMBtu
|
$3.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,262 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,738 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $317 | $200 | - |
$317
-
MMBtu
|
- | |
02 | 2.3212: Optimize plant power factor | $3,024 | $9,555 |
$3,024
-
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $831 | $140 |
$831
26,377
kWh
|
- | - | |
04 | 2.2135: Repair and eliminate steam leaks | $9,402 | $350 | - |
$9,187
-
MMBtu
|
$215 | |
05 | 2.2437: Recover waste heat from equipment | $358 | $468 | - |
$358
-
MMBtu
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $236 | $126 |
$236
7,620
kWh
|
- | - | |
07 | 2.4133: Use most efficient type of electric motors | $595 | $760 |
$595
14,361
kWh
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,254 | $648 |
$3,254
83,236
kWh
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,999 | $1,400 |
$1,999
49,238
kWh
|
- | - | |
10 | 2.2414: Use waste heat from hot flue gases to preheat | $3,246 | $8,400 | - |
$3,246
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $23,262 | $22,047 |
$9,939
180,832
kWh
|
$13,108
-
MMBtu
|
$215 | ||
TOTAL IMPLEMENTED | $13,738 | $3,444 |
$3,661
97,596
kWh
|
$9,862
-
MMBtu
|
$215 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs