ITAC Assessment: OK0167
ITAC logo
ITAC Assessment: OK0167
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product WOOD MOLDINGS
NAICS
n/a
SIC 2431: Millwork
Sales Range $1
M
to 5
M
# of Employees 20
Plant Area
n/a
Annual Production 2,000
thousand feet
Production Hrs. Annual 2,340
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $19,374 283,998
kWh
Natural Gas $9,672 2,298
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,675 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $212 - $212
3,224
kWh
-
02 2.6232: Install set-back timers $187 $70 $187
3,224
kWh
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $82 $80 $82
1,465
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $152 $902 $152
2,638
kWh
-
05 2.7261: Install timers and/or thermostats $138 $200 - $138
-
MMBtu
06 2.7261: Install timers and/or thermostats $2,904 $600 - $2,904
-
MMBtu
TOTAL RECOMMENDED $3,675 $1,852 $633
10,551
kWh
$3,042
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs