Assessment Year | 1985 |
---|---|
Principal Product | WELDED FITTINGS |
NAICS |
n/a
|
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | $5 M to 10M |
# of Employees | 63 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $111,890 | 2,084,408 |
kWh
|
$0.054 |
Natural Gas | $301,549 | 85,792 |
MMBtu
|
$3.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,008 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $6,361 | $1,022 | - |
$6,361
-
MMBtu
|
|
02 | 2.3212: Optimize plant power factor | $900 | $2,355 |
$900
-
kWh
|
- | |
03 | 2.2136: Install / repair insulation on steam lines | $799 | $400 | - |
$799
-
MMBtu
|
|
04 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $146 | $310 | - |
$146
-
MMBtu
|
|
05 | 2.5194: Redesign process | $529 | $33 | - |
$529
-
MMBtu
|
|
06 | 2.2414: Use waste heat from hot flue gases to preheat | $4,273 | $10,000 | - |
$4,273
-
MMBtu
|
|
TOTAL RECOMMENDED | $13,008 | $14,120 |
$900
-
kWh
|
$12,108
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs