ITAC Assessment: OK0152
ITAC logo
ITAC Assessment: OK0152
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product GAS PROCESS EQUIPMENT
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 65
Plant Area
n/a
Annual Production 35
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $19,971 199,883
kWh
Natural Gas $15,804 4,119
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,714 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,159

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $146 $250 - $146
-
MMBtu
02 2.2437: Recover waste heat from equipment $196 $530 - $196
-
MMBtu
03 2.7227: Use water on air conditioning exchanger to improve heat transfer and increase air conditioner efficiency $292 $480 $292
2,931
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $292 $134 $292
2,931
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $204 - $204
2,052
kWh
-
06 2.6232: Install set-back timers $409 - $409
4,103
kWh
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $117 $124 $117
1,172
kWh
-
08 2.7111: Reduce illumination to minimum necessary levels $58 $58 $58
586
kWh
-
TOTAL RECOMMENDED $1,714 $1,576 $1,372
13,775
kWh
$342
-
MMBtu
TOTAL IMPLEMENTED $1,159 $1,326 $963
9,672
kWh
$196
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs