| Assessment Year | 1984 |
|---|---|
| Principal Product | PIPELINE PARTS |
| NAICS |
n/a
|
| SIC | 3519: Internal Combustion Engines, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 90 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 5,330
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $55,067 | 1,065,944 |
kWh
|
$0.052 |
| Natural Gas | $28,276 | 7,574 |
MMBtu
|
$3.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $9,953 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,049 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $142 | $525 | - |
$142
-
MMBtu
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $176 | $450 |
$176
4,396
kWh
|
- | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $28 | - |
$28
586
kWh
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $50 | $46 |
$50
1,172
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $234 | - |
$207
5,275
kWh
|
- | $27 | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,352 | $13,552 |
$6,790
169,695
kWh
|
- | $562 | |
| 07 | 2.2511: Insulate bare equipment | $1,971 | $204 |
$1,702
42,497
kWh
|
$269
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $9,953 | $14,777 |
$8,953
223,621
kWh
|
$411
-
MMBtu
|
$589 | ||
| TOTAL IMPLEMENTED | $2,049 | $250 |
$1,780
44,255
kWh
|
$269
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs