ITAC Assessment: OK0110
ITAC logo
ITAC Assessment: OK0110
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product TANTULUM METAL
NAICS
n/a
SIC 3339: Primary Smelting and Refining of Nonferrous Metals, Except Copper and Aluminum
Sales Range n/a
# of Employees 120
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 8,736
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $609,276 15,327,081
kWh
Natural Gas $195,708 61,059
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,650 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,280

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2443: Re-use or recycle hot or cold process exhaust air $9,373 $20,660 - $9,373
-
MMBtu
02 2.2515: Use optimum thickness insulation $9,453 $3,891 - $9,453
-
MMBtu
03 2.2511: Insulate bare equipment $756 $236 - $756
-
MMBtu
04 2.2511: Insulate bare equipment $389 $405 - $389
-
MMBtu
05 2.1131: Repair faulty insulation in furnaces, boilers, etc $888 $135 $888
33,411
kWh
-
06 2.2122: Install / repair insulation on condensate lines $343 $80 - $343
-
MMBtu
07 2.2122: Install / repair insulation on condensate lines $937 $181 - $937
-
MMBtu
08 2.2122: Install / repair insulation on condensate lines $277 $45 - $277
-
MMBtu
09 2.7261: Install timers and/or thermostats $193 $540 - $193
-
MMBtu
10 2.4221: Install compressor air intakes in coolest locations $41 $148 $41
1,465
kWh
-
TOTAL RECOMMENDED $22,650 $26,321 $929
34,876
kWh
$21,721
-
MMBtu
TOTAL IMPLEMENTED $1,280 $261 - $1,280
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs