ITAC Assessment: OK0053
ITAC logo
ITAC Assessment: OK0053
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product PLASTIC PAILS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area
n/a
Annual Production 5,500,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $283,718 8,020,516
kWh
Natural Gas $2,105 616
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,450 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $54 $38 $54
1,172
kWh
-
02 2.7261: Install timers and/or thermostats $1,297 $470 - $1,297
-
MMBtu
03 2.7226: Use computer programs to optimize hvac performance $1,819 $4,800 $1,819
16,413
kWh
-
04 2.2511: Insulate bare equipment $2,044 $4,000 $2,044
75,615
kWh
-
05 2.3212: Optimize plant power factor $11,988 $8,348 $11,988
-
kWh
-
06 2.4221: Install compressor air intakes in coolest locations $346 $132 $346
12,309
kWh
-
07 2.8122: Use utility controlled power management $902 - $902
-
kWh
-
TOTAL RECOMMENDED $18,450 $17,788 $17,153
105,509
kWh
$1,297
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs