ITAC Assessment: OK0042
ITAC logo
ITAC Assessment: OK0042
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product PULLEYS
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area
n/a
Annual Production 36,000
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $25,937 539,859
kWh
Natural Gas $14,088 5,205
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,764 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7224: Reduce space conditioning during non-working hours $2,978 - - $2,978
-
MMBtu
02 2.4221: Install compressor air intakes in coolest locations $723 $44 $723
14,947
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $35 $14 $35
879
kWh
-
04 2.7447: Install vinyl strip / high speed / air curtain doors $3,698 $728 - $3,698
-
MMBtu
05 2.7142: Utilize higher efficiency lamps and/or ballasts $330 $1,250 $330
7,034
kWh
-
TOTAL RECOMMENDED $7,764 $2,036 $1,088
22,860
kWh
$6,676
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs