Assessment Year | 1982 |
---|---|
Principal Product | CUSTOM STEEL FABRICATION |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
n/a
|
Annual Production | 400,000
pieces
|
Production Hrs. Annual | 2,250
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $78,048 | 2,184,642 |
kWh
|
$0.036 |
Natural Gas | $50,246 | 22,568 |
MMBtu
|
$2.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $3,523 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,523 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,010 | $9,000 |
$2,010
54,220
kWh
|
- | |
02 | 2.7261: Install timers and/or thermostats | $594 | $850 | - |
$594
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $475 | $241 |
$475
11,723
kWh
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $86 | $32 |
$86
3,224
kWh
|
- | |
05 | 2.7492: Use proper thickness of insulation on building envelope | $358 | $158 |
$73
2,052
kWh
|
$285
-
MMBtu
|
|
TOTAL RECOMMENDED | $3,523 | $10,281 |
$2,644
71,219
kWh
|
$879
-
MMBtu
|
||
TOTAL IMPLEMENTED | $3,523 | $10,281 |
$2,644
71,219
kWh
|
$879
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs