Assessment Year 1998
Principal Product Asphalt & Concrete Aggregates
NAICS
n/a
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area
n/a
Annual Production 3,500,000
ton
Production Hrs. Annual 4,653
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $514,814 9,847,304
kWh
Electricity Demand $325,103 45,330
kW-mo/yr
Electricity Fees $29,371 -
Natural Gas $341,499 137,653
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $496,910 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.4221: Install compressor air intakes in coolest locations $215 $58 n/a $209
4,103
kWh
- $6 - -
02 2.2437: Recover waste heat from equipment $768 $661 n/a $746
14,361
kWh
- $22 - -
03 2.2427: Use waste heat from hot flue gases to preheat incoming fluids $9,263 $30,000 n/a - - - $9,263
-
MMBtu
-
04 2.2511: Insulate bare equipment $289 $416 n/a - - - $289
-
MMBtu
-
05 2.4133: Use most efficient type of electric motors $2,645 $4,179 n/a $2,046
39,273
kWh
$527
-
kW-mo/yr
$72 - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $522 $50 n/a $507
9,672
kWh
- $15 - -
07 2.7261: Install timers and/or thermostats $5,436 $175 n/a $5,284
101,114
kWh
- $152 - -
08 4.425: Eliminate/reduce redundant inspections $477,397 $1,400,000 n/a - - - - $477,397
09 3.4151: Minimize water usage $375 $800 n/a $141
2,638
kWh
$224
-
kW-mo/yr
$10 - -
TOTAL RECOMMENDED $496,910 $1,436,339 $8,933
171,161
kWh
$751
-
kW-mo/yr
$277 $9,552
-
MMBtu
$477,397
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs