ITAC Assessment: KS2201
ITAC logo
ITAC Assessment: KS2201
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Fresh Bread and Buns
NAICS 311812: Commercial Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $100
M
to 500
M
# of Employees 243
Plant Area 236,000
ft2
Annual Production 150,000,000
lb
Production Hrs. Annual 4,200
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,020,584 16,522,044
kWh
Natural Gas $474,313 99,618
MMBtu
Waste Disposal Costs
Water Usage $66,607 25,562
Tgal
TOTAL YEARLY COSTS $1,561,504
RECOMMENDED SAVINGS* $155,657 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $84,910

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $11,955 $5,480 $11,955
195,976
kWh
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $5,137 $60 $5,137
84,210
kWh
- -
03 4.661: Level zero – install control systems for existing equipment $1,085 $4,460 $1,085
17,791
kWh
- -
04 2.4226: Use / purchase optimum sized compressor $39,082 $154,800 $39,082
640,689
kWh
- -
05 2.2426: Use waste heat from flue gases to heat space conditioning air $7,820 $2,174 - - $7,820
-
MMBtu
06 2.2511: Insulate bare equipment $868 $1,047 - - $868
-
MMBtu
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $15,572 $61,880 $15,572
255,281
kWh
- -
08 2.9114: Use solar heat to make electricty $60,974 $540,200 $60,974
885,794
kWh
- -
09 2.8118: Check for accuracy of utility / power meters $13,164 $120 - $13,164 -
TOTAL RECOMMENDED $155,657 $770,221 $133,805
2,079,741
kWh
$13,164 $8,688
-
MMBtu
TOTAL IMPLEMENTED $84,910 $222,340 $71,746
1,176,156
kWh
$13,164 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs