ITAC Assessment: NV0091
ITAC logo
ITAC Assessment: NV0091
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Hot-Melt Adhesives
NAICS
n/a
SIC 2891: Adhesives and Sealants
Sales Range $10
M
to 50
M
# of Employees 20
Plant Area 30,000
ft2
Annual Production 13,500,000
lb
Production Hrs. Annual 6,528
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,153 707,796
kWh
Electricity Demand $20,611 2,221
kW-mo/yr
Electricity Fees $1,635 -
Natural Gas $31,681 6,073
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,277 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,838

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings
01 2.7111: Reduce illumination to minimum necessary levels $4,073 $245 $2,935
66,823
kWh
$1,138
-
kW-mo/yr
- - -
02 2.7135: Install occupancy sensors $425 $62 $332
7,620
kWh
$93
-
kW-mo/yr
- - -
03 2.7261: Install timers and/or thermostats $6,435 $380 - - $6,435
-
MMBtu
- -
04 2.1133: Adjust burners for efficient operation $1,330 $400 - - $1,330
-
MMBtu
- -
05 2.4221: Install compressor air intakes in coolest locations $262 $500 $262
5,862
kWh
- - - -
06 3.4151: Minimize water usage $170 $900 - - - $170
-
Tgal
-
07 4.131: Modify process to reduce material use/cost $582 $220 - - - - $582
TOTAL RECOMMENDED $13,277 $2,707 $3,529
80,305
kWh
$1,231
-
kW-mo/yr
$7,765
-
MMBtu
$170
-
Tgal
$582
TOTAL IMPLEMENTED $11,838 $1,025 $2,935
66,823
kWh
$1,138
-
kW-mo/yr
$7,765
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs