Assessment Year | 1997 |
---|---|
Principal Product | Hot-Melt Adhesives |
NAICS |
n/a
|
SIC | 2891: Adhesives and Sealants |
Sales Range | $10 M to 50M |
# of Employees | 20 |
Plant Area |
30,000
ft2
|
Annual Production | 13,500,000
lb
|
Production Hrs. Annual | 6,528
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $31,153 | 707,796 |
kWh
|
$0.044 |
Electricity Demand | $20,611 | 2,221 |
kW-mo/yr
|
$9.28 |
Electricity Fees | $1,635 | - |
|
- |
Natural Gas | $31,681 | 6,073 |
MMBtu
|
$5.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,277 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,838 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $4,073 | $245 |
$2,935
66,823
kWh
|
$1,138
-
kW-mo/yr
|
- | - | - | |
02 | 2.7135: Install occupancy sensors | $425 | $62 |
$332
7,620
kWh
|
$93
-
kW-mo/yr
|
- | - | - | |
03 | 2.7261: Install timers and/or thermostats | $6,435 | $380 | - | - |
$6,435
-
MMBtu
|
- | - | |
04 | 2.1133: Adjust burners for efficient operation | $1,330 | $400 | - | - |
$1,330
-
MMBtu
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $262 | $500 |
$262
5,862
kWh
|
- | - | - | - | |
06 | 3.4151: Minimize water usage | $170 | $900 | - | - | - |
$170
-
Tgal
|
- | |
07 | 4.131: Modify process to reduce material use/cost | $582 | $220 | - | - | - | - | $582 | |
TOTAL RECOMMENDED | $13,277 | $2,707 |
$3,529
80,305
kWh
|
$1,231
-
kW-mo/yr
|
$7,765
-
MMBtu
|
$170
-
Tgal
|
$582 | ||
TOTAL IMPLEMENTED | $11,838 | $1,025 |
$2,935
66,823
kWh
|
$1,138
-
kW-mo/yr
|
$7,765
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs