ITAC Assessment: NV0081
ITAC logo
ITAC Assessment: NV0081
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Steel Doors
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $100
M
to 500
M
# of Employees 52
Plant Area 120,000
ft2
Annual Production 5,000
thousand feet
Production Hrs. Annual 3,320
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $75,951 1,121,336
kWh
Electricity Demand $28,424 3,651
kW-mo/yr
Electricity Fees $4,784 -
Natural Gas $7,066 1,223
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $130,624 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $75,254

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Product Savings
01 2.4133: Use most efficient type of electric motors $3,967 $170 $2,976
43,962
kWh
$991
-
kW-mo/yr
- - -
02 2.7261: Install timers and/or thermostats $2,948 $1,330 - - $2,948
-
MMBtu
- -
03 2.2437: Recover waste heat from equipment $2,173 $1,500 - - $2,173
-
MMBtu
- -
04 2.4221: Install compressor air intakes in coolest locations $872 $360 $750
7,620
kWh
$122
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $435 $32 $276
4,103
kWh
$159
-
kW-mo/yr
- - -
06 2.2515: Use optimum thickness insulation $2,717 $11,160 - - $2,717
-
MMBtu
- -
07 4.112: Replace old machine with new automatic multi-station tool $1,164 $2,120 $1,203
17,878
kWh
$(-39.0)
-
kW-mo/yr
- - -
08 4.111: Add equipment/ operators to reduce production bottleneck $30,328 $155,000 - - - - $30,328
09 4.122: Develop standard procedures to improve internal yields $60,656 $12,000 - - - - $60,656
10 4.111: Add equipment/ operators to reduce production bottleneck $15,164 $20,000 - - - - $15,164
11 3.5315: Lease / purchase baler; sell cardboard to recycler $8,160 $20,000 - - - $8,160
-
lb
-
12 4.221: Use only amount of packaging material necessary $2,040 - - - - $2,040
-
lb
-
TOTAL RECOMMENDED $130,624 $223,672 $5,205
73,563
kWh
$1,233
-
kW-mo/yr
$7,838
-
MMBtu
$10,200
-
lb
$106,148
TOTAL IMPLEMENTED $75,254 $34,682 $5,205
73,563
kWh
$1,233
-
kW-mo/yr
- $8,160
-
lb
$60,656
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs