Assessment Year | 2021 |
---|---|
Principal Product | stringers and frames for commercial airplanes |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 1,500 |
Plant Area |
615,000
ft2
|
Annual Production | 36
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $935,021 | 26,022,921 |
kWh
|
$0.036 |
Electricity Demand | $975,042 | 56,689 |
kW-mo/yr
|
$17.20 |
Electricity Fees | $175,886 | - |
|
- |
Natural Gas | $348,786 | 70,870 |
MMBtu
|
$4.92 |
TOTAL YEARLY COSTS | $2,434,735 | |||
RECOMMENDED SAVINGS* | $98,806 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $94,072 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $52,219 | $52,219 |
$31,579
877,183
kWh
|
$20,640
-
kW-mo/yr
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $28,872 | $40,613 |
$15,456
429,334
kWh
|
$13,416
-
kW-mo/yr
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,994 | $15,475 |
$2,758
76,485
kWh
|
$2,236
-
kW-mo/yr
|
- | - | |
04 | 2.3212: Optimize plant power factor | $3,945 | $5,606 | - | - | $3,945 | - | |
05 | 2.7135: Install occupancy sensors | $2,978 | $3,520 |
$2,978
82,879
kWh
|
- | - | - | |
06 | 2.6218: Turn off equipment when not in use | $4,269 | $1,000 |
$1,849
51,364
kWh
|
$2,420
-
kW-mo/yr
|
- | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $1,064 | $4,892 |
$643
17,888
kWh
|
$421
-
kW-mo/yr
|
- | - | |
08 | 2.8114: Change rate schedules or other changes in utility service | $464 | $100 | - | - | - | $464 | |
TOTAL RECOMMENDED | $98,806 | $123,425 |
$55,263
1,535,132
kWh
|
$39,134
-
kW-mo/yr
|
$3,945 | $464 | ||
TOTAL IMPLEMENTED | $94,072 | $122,325 |
$53,414
1,483,769
kWh
|
$36,713
-
kW-mo/yr
|
$3,945 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs