Assessment Year | 1997 |
---|---|
Principal Product | Precison Sheet Metal |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
84,000
ft2
|
Annual Production | 3,000,000
lb
|
Production Hrs. Annual | 5,824
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $55,499 | 1,271,981 |
kWh
|
$0.044 |
Electricity Demand | $25,691 | 2,736 |
kW-mo/yr
|
$9.39 |
Electricity Fees | $2,056 | - |
|
- |
Natural Gas | $31,131 | 6,133 |
MMBtu
|
$5.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $188,225 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $115,275 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $878 | $54 |
$321
7,327
kWh
|
$113
-
kW-mo/yr
|
$444 | - | - | - | |
02 | 2.7261: Install timers and/or thermostats | $7,471 | $2,850 | - | - | - |
$7,471
-
MMBtu
|
- | - | |
03 | 2.7135: Install occupancy sensors | $146 | $186 |
$101
2,345
kWh
|
$45
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $310 | $360 |
$186
6,448
kWh
|
$124
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $691 | $70 |
$398
9,086
kWh
|
$293
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,156 | $400 |
$1,156
26,377
kWh
|
- | - | - | - | - | |
07 | 2.2531: Re-size charging openings or add movable cover or door | $645 | $589 | - | - | - |
$645
-
MMBtu
|
- | - | |
08 | 4.322: Eliminate old stock and modify inventory control | $111,690 | $110,000 | - | - | - | - | - | $111,690 | |
09 | 4.212: Adopt in-house material generation | $60,000 | $50,000 | - | - | - | - | - | $60,000 | |
10 | 4.821: Pay bills on time to avoid late fees | $438 | - | - | - | - | - | - | $438 | |
11 | 3.5311: Recover and reuse waste material | $3,600 | $300 | - | - | - | - |
$3,600
-
lb
|
- | |
12 | 3.5311: Recover and reuse waste material | $1,200 | - | - | - | - | - |
$1,200
-
lb
|
- | |
TOTAL RECOMMENDED | $188,225 | $164,809 |
$2,162
51,583
kWh
|
$575
-
kW-mo/yr
|
$444 |
$8,116
-
MMBtu
|
$4,800
-
lb
|
$172,128 | ||
TOTAL IMPLEMENTED | $115,275 | $111,175 |
$1,257
28,722
kWh
|
$45
-
kW-mo/yr
|
- |
$645
-
MMBtu
|
$1,200
-
lb
|
$112,128 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs