Assessment Year | 1995 |
---|---|
Principal Product | Automotive Ignition Systems and Camshafts |
NAICS |
n/a
|
SIC | 3694: Electrical Equipment for Internal Combustion Engines |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
113,000
ft2
|
Annual Production | 2,000,000
pieces
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $165,452 | 2,398,007 |
kWh
|
$0.069 |
Natural Gas | $23,003 | 3,710 |
MMBtu
|
$6.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,963 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,258 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $810 | $1,291 |
$810
11,723
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,075 | $300 |
$1,075
21,688
kWh
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $539 | $318 |
$539
10,844
kWh
|
- | |
04 | 2.2511: Insulate bare equipment | $589 | $196 |
$589
12,016
kWh
|
- | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $1,346 | $2,000 |
$1,346
22,567
kWh
|
- | |
06 | 2.7144: Install spectral reflectors / delamp | $814 | - |
$814
13,189
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,003 | $205 |
$2,003
34,291
kWh
|
- | |
08 | 2.6218: Turn off equipment when not in use | $370 | - |
$370
7,327
kWh
|
- | |
09 | 2.7261: Install timers and/or thermostats | $3,417 | $1,504 | - |
$3,417
-
MMBtu
|
|
TOTAL RECOMMENDED | $10,963 | $5,814 |
$7,546
133,645
kWh
|
$3,417
-
MMBtu
|
||
TOTAL IMPLEMENTED | $4,258 | $1,796 |
$4,258
75,029
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs