Assessment Year | 1995 |
---|---|
Principal Product | Concrete Pipes |
NAICS |
n/a
|
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $1 M to 5M |
# of Employees | 17 |
Plant Area |
18,400
ft2
|
Annual Production | 35,000
ton
|
Production Hrs. Annual | 2,730
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,630 | 372,509 |
kWh
|
$0.096 |
Natural Gas | $18,782 | 3,620 |
MMBtu
|
$5.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,759 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,219 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,565 | $1,264 |
$1,565
16,413
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $183 | $76 |
$183
2,052
kWh
|
- | |
03 | 2.7261: Install timers and/or thermostats | $972 | $320 | - |
$972
-
MMBtu
|
|
04 | 2.2136: Install / repair insulation on steam lines | $166 | $44 | - |
$166
-
MMBtu
|
|
05 | 2.2511: Insulate bare equipment | $1,416 | $220 | - |
$1,416
-
MMBtu
|
|
06 | 2.2511: Insulate bare equipment | $2,224 | $3,088 | - |
$2,224
-
MMBtu
|
|
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,665 | $200 |
$1,665
17,585
kWh
|
- | |
08 | 2.4221: Install compressor air intakes in coolest locations | $568 | $180 |
$568
5,862
kWh
|
- | |
TOTAL RECOMMENDED | $8,759 | $5,392 |
$3,981
41,912
kWh
|
$4,778
-
MMBtu
|
||
TOTAL IMPLEMENTED | $4,219 | $784 |
$1,665
17,585
kWh
|
$2,554
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs