Assessment Year | 2023 |
---|---|
Principal Product | Mining Machinery and Equipment |
NAICS | 333131: Mining Machinery and Equipment Manufacturing |
SIC | 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
250,000
ft2
|
Annual Production | 1,451
pieces
|
Production Hrs. Annual | 5,760
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $978,683 | 8,983,661 |
kWh
|
$0.11 | |
Electricity Demand | $184,810 | 20,983 |
kW-mo/yr
|
$8.81 | |
Electricity Fees | $93,617 | - |
|
- | |
Natural Gas | $8,645 | 814 |
MMBtu
|
$10.62 | |
Waste Disposal Costs | |||||
Water Usage | $76,548 | 7,316 |
Tgal
|
$10.46 | |
TOTAL YEARLY COSTS | $1,342,302 | ||||
RECOMMENDED SAVINGS* | $233,422 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $34,941 | $10,056 |
$34,941
323,524
kWh
|
- | - | - | |
02 | 2.7221: Lower temperature during the winter season and vice-versa | $1,685 | - |
$1,685
15,476
kWh
|
- | - | - | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $15,942 | - |
$15,942
146,390
kWh
|
- | - | - | |
04 | 2.3212: Optimize plant power factor | $12,361 | $27,064 | - |
$12,361
-
kW-mo/yr
|
- | - | |
05 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $16,552 | - |
$15,683
144,014
kWh
|
$869
-
kW-mo/yr
|
- | - | |
06 | 2.2622: Replace existing chiller with high efficiency model | $151,941 | $2,205,000 |
$34,475
316,577
kWh
|
$11,602
-
kW-mo/yr
|
$57,864
-
Tgal
|
$48,000 | |
TOTAL RECOMMENDED | $233,422 | $2,242,120 |
$102,726
945,981
kWh
|
$24,832
-
kW-mo/yr
|
$57,864
-
Tgal
|
$48,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs