Assessment Year | 2022 |
---|---|
Principal Product | Precast Concrete |
NAICS | 327390: Other Concrete Product Manufacturing |
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
1,450,000
ft2
|
Annual Production | 10,503
Tgal
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $63,840 | 978,584 |
kWh
|
$0.065 | |
Electricity Demand | $24,205 | 4,499 |
kW-mo/yr
|
$5.38 | |
Electricity Fees | $2,297 | - |
|
- | |
Natural Gas | $65,557 | 17,176 |
MMBtu
|
$3.82 | |
Other Gas | $29,503 | 1 |
MMBtu
|
$29,503.00 | |
Waste Disposal Costs | |||||
Water Usage | $1 | 1 |
Tgal
|
$1.00 | |
TOTAL YEARLY COSTS | $185,403 | ||||
RECOMMENDED SAVINGS* | $6,114 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,101 | $2,000 |
$2,881
44,188
kWh
|
- | $(-680.0) | - | $(-100.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,901 | $3,265 |
$1,342
20,579
kWh
|
$429
-
kW-mo/yr
|
$131 | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,230 | $2,400 |
$1,028
15,768
kWh
|
$181
-
kW-mo/yr
|
$21 | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $505 | $2,425 |
$505
7,740
kWh
|
- | - | - | - | |
05 | 4.821: Pay bills on time to avoid late fees | $377 | $85 | - | - | - | $377 | - | |
TOTAL RECOMMENDED | $6,114 | $10,175 |
$5,756
88,275
kWh
|
$609
-
kW-mo/yr
|
$(-528.0) | $377 | $(-100.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs