Assessment Year | 2019 |
---|---|
Principal Product | Blood and Urine Collection Products |
NAICS | 339112: Surgical and Medical Instrument Manufacturing |
SIC | 3841: Surgical and Medical Instruments and Apparatus |
Sales Range | $100 M to 500M |
# of Employees | 563 |
Plant Area |
300,000
ft2
|
Annual Production | 4,000,000,000
units
|
Production Hrs. Annual | 8,064
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $2,719,321 | 48,735,604 |
kWh
|
$0.056 | |
Electricity Demand | $1,296,943 | 81,594 |
kW-mo/yr
|
$15.90 | |
Electricity Fees | $22,673 | - |
|
- | |
Natural Gas | $170,136 | 32,053 |
MMBtu
|
$5.31 | |
Waste Disposal Costs | |||||
Water Usage | $174,574 | 91,561 |
Tgal
|
$1.91 | |
Water Disposal | $193,855 | 91,561 |
Tgal
|
$2.12 | |
TOTAL YEARLY COSTS | $4,577,502 | ||||
RECOMMENDED SAVINGS* | $218,597 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $62,950 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $106,822 | $130,000 | - | - | - | - | - | - | - | - | $106,822 | |
02 | 4.652: Replace existing equipment with more suitable substitutes | $38,925 | $150,000 |
$27,366
488,678
kWh
|
$11,559
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 3.4116: Meter recycled water (to reduce sewer charges) | $25,402 | $1,697 | - | - | - | - |
$25,402
-
Tgal
|
- | - | - | - | |
04 | 2.2113: Repair or replace steam traps | $16,450 | $4,500 | - | - |
$18,250
-
MMBtu
|
- | - | $(-1,800.0) | - | - | - | |
05 | 2.7444: Close holes and openings in building such as broken windows | $10,400 | $51,350 | - | - | - | - | - | - | - | - | $10,400 | |
06 | 3.5314: Use in-process recycling whenever possible | $9,900 | $3,660 | - | - | - | - | - | - | $9,900 | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,049 | $18,439 |
$9,589
171,197
kWh
|
- | - | - | - | $(-1,440.0) | - | $(-100.0) | - | |
08 | 3.5131: Recycle white water | $2,649 | $1,000 | - | - | - |
$408
-
Tgal
|
$600
-
Tgal
|
- | - | $1,641 | - | |
TOTAL RECOMMENDED | $218,597 | $360,646 |
$36,955
659,875
kWh
|
$11,559
-
kW-mo/yr
|
$18,250
-
MMBtu
|
$408
-
Tgal
|
$26,002
-
Tgal
|
$(-3,240.0) | $9,900 | $1,541 | $117,222 | ||
TOTAL IMPLEMENTED | $62,950 | $76,986 |
$9,589
171,197
kWh
|
- |
$18,250
-
MMBtu
|
$408
-
Tgal
|
$26,002
-
Tgal
|
$(-3,240.0) | - | $1,541 | $10,400 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs