| Assessment Year | 1996 |
|---|---|
| Principal Product | Bulk Materials Handling Equipment |
| NAICS |
n/a
|
| SIC | 3535: Conveyors and Conveying Equipment |
| Sales Range | $5 M to 10M |
| # of Employees | 60 |
| Plant Area |
20,000
ft2
|
| Annual Production | 250
pieces
|
| Production Hrs. Annual | 2,040
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $27,732 | 545,721 |
kWh
|
$0.051 |
| Natural Gas | $17,379 | 3,251 |
MMBtu
|
$5.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,014 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,979 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $40 | $537 |
$40
879
kWh
|
- | - | - | - | |
| 02 | 2.7261: Install timers and/or thermostats | $1,502 | $500 | - |
$1,502
-
MMBtu
|
- | - | - | |
| 03 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $49 | - | - | - |
$49
-
lb
|
- | - | |
| 04 | 3.1191: Change procedures / equipment / operating conditions | $100 | $190 | - | - | - | - | $100 | |
| 05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $393 | - | - | - |
$393
-
lb
|
- | - | |
| 06 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $15,930 | $7,600 | - | - | - | $15,600 | $330 | |
| TOTAL RECOMMENDED | $18,014 | $8,827 |
$40
879
kWh
|
$1,502
-
MMBtu
|
$442
-
lb
|
$15,600 | $430 | ||
| TOTAL IMPLEMENTED | $15,979 | $7,600 | - | - |
$49
-
lb
|
$15,600 | $330 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs