Assessment Year | 1996 |
---|---|
Principal Product | Bulk Materials Handling Equipment |
NAICS |
n/a
|
SIC | 3535: Conveyors and Conveying Equipment |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
20,000
ft2
|
Annual Production | 250
pieces
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,732 | 545,721 |
kWh
|
$0.051 |
Natural Gas | $17,379 | 3,251 |
MMBtu
|
$5.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,014 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,979 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $40 | $537 |
$40
879
kWh
|
- | - | - | - | |
02 | 2.7261: Install timers and/or thermostats | $1,502 | $500 | - |
$1,502
-
MMBtu
|
- | - | - | |
03 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $49 | - | - | - |
$49
-
lb
|
- | - | |
04 | 3.1191: Change procedures / equipment / operating conditions | $100 | $190 | - | - | - | - | $100 | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $393 | - | - | - |
$393
-
lb
|
- | - | |
06 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $15,930 | $7,600 | - | - | - | $15,600 | $330 | |
TOTAL RECOMMENDED | $18,014 | $8,827 |
$40
879
kWh
|
$1,502
-
MMBtu
|
$442
-
lb
|
$15,600 | $430 | ||
TOTAL IMPLEMENTED | $15,979 | $7,600 | - | - |
$49
-
lb
|
$15,600 | $330 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs