ITAC Assessment: UL0173
ITAC logo
ITAC Assessment: UL0173
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Bulk Materials Handling Equipment
NAICS
n/a
SIC 3535: Conveyors and Conveying Equipment
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 20,000
ft2
Annual Production 250
pieces
Production Hrs. Annual 2,040
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $27,732 545,721
kWh
Natural Gas $17,379 3,251
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,014 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,979

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $40 $537 $40
879
kWh
- - - -
02 2.7261: Install timers and/or thermostats $1,502 $500 - $1,502
-
MMBtu
- - -
03 3.5248: Separate and recycle scrap metal to foundry or for sale $49 - - - $49
-
lb
- -
04 3.1191: Change procedures / equipment / operating conditions $100 $190 - - - - $100
05 3.5315: Lease / purchase baler; sell cardboard to recycler $393 - - - $393
-
lb
- -
06 3.2123: Convert to high volume low pressure (hvlp) paint guns $15,930 $7,600 - - - $15,600 $330
TOTAL RECOMMENDED $18,014 $8,827 $40
879
kWh
$1,502
-
MMBtu
$442
-
lb
$15,600 $430
TOTAL IMPLEMENTED $15,979 $7,600 - - $49
-
lb
$15,600 $330
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs