ITAC Assessment: ND0356
ITAC logo
ITAC Assessment: ND0356
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Aluminum Entrance Systems
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 139
Plant Area 78,500
ft2
Annual Production 19,122
pieces
Production Hrs. Annual 4,680
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $105,504 1,899,472
kWh
Electricity Demand $23,842 6,036
kW-mo/yr
Natural Gas $34,914 9,130
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,802 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,495

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $4,224 $853 $3,648
63,306
kWh
$576
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $885 $220 $885
15,240
kWh
- - - -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $419 $400 $306
5,275
kWh
$199
-
kW-mo/yr
$(-86.0)
-
MMBtu
- -
04 2.6218: Turn off equipment when not in use $309 $40 $266
4,689
kWh
$43
-
kW-mo/yr
- - -
05 2.4151: Develop a repair/replace policy $584 $2,012 $484
8,499
kWh
$100
-
kW-mo/yr
- - -
06 2.7135: Install occupancy sensors $353 $300 $294
4,982
kWh
$59
-
kW-mo/yr
- - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $11,843 $8,685 $8,340
144,490
kWh
$1,463
-
kW-mo/yr
- $761 $1,279
08 2.4221: Install compressor air intakes in coolest locations $527 $600 $448
7,913
kWh
$79
-
kW-mo/yr
- - -
09 2.7111: Reduce illumination to minimum necessary levels $658 $200 $560
9,672
kWh
$98
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $19,802 $13,310 $15,231
264,066
kWh
$2,617
-
kW-mo/yr
$(-86.0)
-
MMBtu
$761 $1,279
TOTAL IMPLEMENTED $6,495 $1,713 $5,665
98,182
kWh
$916
-
kW-mo/yr
$(-86.0)
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs