Assessment Year | 2000 |
---|---|
Principal Product | Brass Plumbing Fixtures |
NAICS |
n/a
|
SIC | 3432: Plumbing Fixture Fittings and Trim |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
164,644
ft2
|
Annual Production | 7,000,000
lb
|
Production Hrs. Annual | 4,463
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $233,994 | 14,242,673 |
kWh
|
$0.016 |
Electricity Demand | $446,750 | 39,396 |
kW-mo/yr
|
$11.34 |
Natural Gas | $164,986 | 40,326 |
MMBtu
|
$4.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,816 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,671 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $355 | $240 |
$355
21,688
kWh
|
- | - | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $415 | $660 |
$61
3,810
kWh
|
$59
-
kW-mo/yr
|
- | - | - | $175 | $120 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,533 | $14,644 |
$720
43,669
kWh
|
$1,813
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,145 | $2,970 |
$319
19,343
kWh
|
$2,164
-
kW-mo/yr
|
- |
$(-338.0)
-
MMBtu
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,506 | $300 |
$778
47,186
kWh
|
$728
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.4151: Develop a repair/replace policy | $8,446 | $27,572 |
$1,741
105,803
kWh
|
$6,705
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 3.4151: Minimize water usage | $2,685 | $6,840 | - | - | - | - |
$2,685
-
Tgal
|
- | - | |
08 | 4.821: Pay bills on time to avoid late fees | $1,731 | - | - | - | $1,731 | - | - | - | - | |
TOTAL RECOMMENDED | $19,816 | $53,226 |
$3,974
241,499
kWh
|
$11,469
-
kW-mo/yr
|
$1,731 |
$(-338.0)
-
MMBtu
|
$2,685
-
Tgal
|
$175 | $120 | ||
TOTAL IMPLEMENTED | $17,671 | $50,256 |
$3,655
222,156
kWh
|
$9,305
-
kW-mo/yr
|
$1,731 | - |
$2,685
-
Tgal
|
$175 | $120 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs