ITAC Assessment: UL2210
ITAC logo
ITAC Assessment: UL2210
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product automotive carpet
NAICS 314110: Carpet and Rug Mills
SIC 2273: Carpets and Rugs
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 60,000
ft2
Annual Production 2,106
ton
Production Hrs. Annual 6,600
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $659,281 11,221,800
kWh
Electricity Demand $373,363 30,806
kW-mo/yr
Electricity Fees $98,721 -
Natural Gas $187,381 20,594
MMBtu
Waste Disposal Costs
Water Usage $44,154 8,205
Tgal
Water Disposal $92,790 8,205
Tgal
TOTAL YEARLY COSTS $1,455,690
RECOMMENDED SAVINGS* $192,700 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $38,110

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $22,273 $11,544 $16,947
287,244
kWh
$5,326
-
kW-mo/yr
-
02 2.7111: Reduce illumination to minimum necessary levels $6,394 - $4,851
82,574
kWh
$1,543
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $4,208 - $4,208
71,314
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,235 $1,600 $5,235
88,725
kWh
- -
05 2.9114: Use solar heat to make electricty $86,119 $765,706 $62,040
1,051,526
kWh
$24,079
-
kW-mo/yr
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,669 $20,000 $5,669
96,091
kWh
- -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,109 $20,000 $3,109
52,697
kWh
- -
08 2.9112: Use solar heat to heat water $59,693 $150,000 - - $59,693
-
MMBtu
TOTAL RECOMMENDED $192,700 $968,850 $102,059
1,730,171
kWh
$30,948
-
kW-mo/yr
$59,693
-
MMBtu
TOTAL IMPLEMENTED $38,110 $13,144 $31,241
529,857
kWh
$6,869
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs