Assessment Year | 2000 |
---|---|
Principal Product | Abrasives and Air Filters |
NAICS |
n/a
|
SIC | 3291: Abrasive Products |
Sales Range | $10 M to 50M |
# of Employees | 139 |
Plant Area |
200,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,290
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $180,917 | 2,915,299 |
kWh
|
$0.062 |
Electricity Demand | $81,009 | 10,485 |
kW-mo/yr
|
$7.73 |
Natural Gas | $176,139 | 44,333 |
MMBtu
|
$3.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,218 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,331 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,237 | $10,801 |
$1,472
24,912
kWh
|
$765
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.7135: Install occupancy sensors | $573 | $600 |
$425
6,741
kWh
|
$148
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,205 | $11,337 |
$1,201
19,343
kWh
|
$419
-
kW-mo/yr
|
- | - | $975 | - | $1,610 | |
04 | 2.4221: Install compressor air intakes in coolest locations | $3,489 | $300 |
$2,970
47,773
kWh
|
$519
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,107 | $140 |
$1,107
17,878
kWh
|
- | - | - | - | - | - | |
06 | 2.4151: Develop a repair/replace policy | $1,117 | $1,714 |
$828
13,482
kWh
|
$289
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.2443: Re-use or recycle hot or cold process exhaust air | $4,286 | $8,120 | - | - |
$4,286
-
MMBtu
|
- | - | - | - | |
08 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $20,782 | $25,000 | - |
$20,782
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 3.4151: Minimize water usage | $1,028 | $4,025 | - | - | - |
$1,028
-
Tgal
|
- | - | - | |
10 | 3.4155: Meter waste water | $1,127 | $200 | - | - | - |
$1,127
-
Tgal
|
- | - | - | |
11 | 2.8121: Apply for tax-free status for energy purchases | $267 | $200 | - | - | - | - | - | $267 | - | |
TOTAL RECOMMENDED | $40,218 | $62,437 |
$8,003
130,129
kWh
|
$22,922
-
kW-mo/yr
|
$4,286
-
MMBtu
|
$2,155
-
Tgal
|
$975 | $267 | $1,610 | ||
TOTAL IMPLEMENTED | $34,331 | $49,692 |
$7,578
123,388
kWh
|
$22,774
-
kW-mo/yr
|
- |
$1,127
-
Tgal
|
$975 | $267 | $1,610 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs