Assessment Year | 1999 |
---|---|
Principal Product | Orthopedic Products |
NAICS |
n/a
|
SIC | 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies |
Sales Range | $5 M to 10M |
# of Employees | 110 |
Plant Area |
36,800
ft2
|
Annual Production | 2,000,000
pieces
|
Production Hrs. Annual | 2,250
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $71,863 | 1,358,734 |
kWh
|
$0.053 |
Electricity Demand | $20,320 | 4,761 |
kW-mo/yr
|
$4.27 |
Natural Gas | $9,441 | 1,831 |
MMBtu
|
$5.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,790 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,336 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $1,714 | $1,600 |
$1,349
28,429
kWh
|
$365
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4226: Use / purchase optimum sized compressor | $1,675 | $500 |
$1,675
35,463
kWh
|
- | - | - | - | - | |
03 | 2.4151: Develop a repair/replace policy | $992 | $2,732 |
$753
15,826
kWh
|
$239
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7144: Install spectral reflectors / delamp | $899 | $300 |
$713
15,240
kWh
|
$186
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,077 | $220 |
$1,077
22,860
kWh
|
- | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $532 | $595 |
$339
7,327
kWh
|
$42
-
kW-mo/yr
|
- | - | $151 | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $372 | $200 |
$358
7,620
kWh
|
$14
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.6218: Turn off equipment when not in use | $61 | $45 |
$61
1,172
kWh
|
- | - | - | - | - | |
09 | 3.5316: Contract a wood pallet recycling company | $360 | $360 | - | - | - | - | $360 | - | |
10 | 2.8114: Change rate schedules or other changes in utility service | $1,533 | $80 | - | - | - |
$1,397
-
MMBtu
|
- |
$136
-
Tgal
|
|
11 | 2.8114: Change rate schedules or other changes in utility service | $575 | $200 | - | - | $575 | - | - | - | |
TOTAL RECOMMENDED | $9,790 | $6,832 |
$6,325
133,937
kWh
|
$846
-
kW-mo/yr
|
$575 |
$1,397
-
MMBtu
|
$511 |
$136
-
Tgal
|
||
TOTAL IMPLEMENTED | $2,336 | $880 |
$1,790
38,100
kWh
|
$186
-
kW-mo/yr
|
- | - | $360 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs