ITAC Assessment: AR0098
ITAC logo
ITAC Assessment: AR0098
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Water Faucets
NAICS
n/a
SIC 3088: Plastics Plumbing Fixtures
Sales Range $500
k
to 1
M
# of Employees 175
Plant Area 40,000
ft2
Annual Production 1,040,000
pieces
Production Hrs. Annual 7,508
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $90,609 1,054,513
kWh
Electricity Demand $13,767 3,304
kW-mo/yr
Natural Gas $4,094 651
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,976 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,876

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
01 2.2511: Insulate bare equipment $1,071 $140 $982
13,482
kWh
$89
-
kW-mo/yr
- -
02 2.4221: Install compressor air intakes in coolest locations $203 $50 $186
2,638
kWh
$17
-
kW-mo/yr
- -
03 2.7111: Reduce illumination to minimum necessary levels $3,535 $751 $3,211
43,962
kWh
$324
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,272 $235 $1,166
16,120
kWh
$106
-
kW-mo/yr
- -
05 2.4133: Use most efficient type of electric motors $1,858 $1,460 $1,676
22,860
kWh
$182
-
kW-mo/yr
- -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $577 - $515
7,034
kWh
$62
-
kW-mo/yr
- -
07 3.7311: Maintain machines to reduce leaks $3,360 $600 - - $3,360
-
gal
-
08 2.8211: Consolidate freight shipments and/or deliveries $9,100 - - - - $9,100
TOTAL RECOMMENDED $20,976 $3,236 $7,736
106,096
kWh
$780
-
kW-mo/yr
$3,360
-
gal
$9,100
TOTAL IMPLEMENTED $11,876 $3,236 $7,736
106,096
kWh
$780
-
kW-mo/yr
$3,360
-
gal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs