ITAC Assessment: ND0311
ITAC logo
ITAC Assessment: ND0311
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Canned Soft Drinks
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 36
Plant Area 76,000
ft2
Annual Production 312,000,000
pieces
Production Hrs. Annual 3,400
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $74,154 2,402,989
kWh
Electricity Demand $77,712 7,836
kW-mo/yr
Natural Gas $61,342 13,842
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,728 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,118

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2442: Preheat combustion air with waste heat $6,319 $10,000 - - $6,319
-
MMBtu
- -
02 4.611: Begin a practice of predictive / preventative maintenance $2,788 $200 - - - $2,788 -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,079 $5,300 $458
14,947
kWh
$621
-
kW-mo/yr
- - -
04 2.6231: Utilize controls to operate equipment only when needed $704 $2,300 $704
22,860
kWh
- - - -
05 2.7111: Reduce illumination to minimum necessary levels $698 - $327
10,551
kWh
$371
-
kW-mo/yr
- - -
06 2.4221: Install compressor air intakes in coolest locations $414 $450 $414
13,482
kWh
- - - -
07 2.7144: Install spectral reflectors / delamp $392 $875 $144
4,689
kWh
$248
-
kW-mo/yr
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $248 $500 $49
1,465
kWh
$22
-
kW-mo/yr
- - $177
09 2.7135: Install occupancy sensors $65 $200 $65
2,052
kWh
- - - -
10 2.6218: Turn off equipment when not in use $21 $53 $21
586
kWh
- - - -
TOTAL RECOMMENDED $12,728 $19,878 $2,182
70,632
kWh
$1,262
-
kW-mo/yr
$6,319
-
MMBtu
$2,788 $177
TOTAL IMPLEMENTED $1,118 $2,750 $1,118
36,342
kWh
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs