| Assessment Year | 1998 |
|---|---|
| Principal Product | Canned Soft Drinks |
| NAICS |
n/a
|
| SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
| Sales Range | $10 M to 50M |
| # of Employees | 36 |
| Plant Area |
76,000
ft2
|
| Annual Production | 312,000,000
pieces
|
| Production Hrs. Annual | 3,400
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $74,154 | 2,402,989 |
kWh
|
$0.031 |
| Electricity Demand | $77,712 | 7,836 |
kW-mo/yr
|
$9.92 |
| Natural Gas | $61,342 | 13,842 |
MMBtu
|
$4.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,728 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,118 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2442: Preheat combustion air with waste heat | $6,319 | $10,000 | - | - |
$6,319
-
MMBtu
|
- | - | |
| 02 | 4.611: Begin a practice of predictive / preventative maintenance | $2,788 | $200 | - | - | - | $2,788 | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,079 | $5,300 |
$458
14,947
kWh
|
$621
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.6231: Utilize controls to operate equipment only when needed | $704 | $2,300 |
$704
22,860
kWh
|
- | - | - | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $698 | - |
$327
10,551
kWh
|
$371
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $414 | $450 |
$414
13,482
kWh
|
- | - | - | - | |
| 07 | 2.7144: Install spectral reflectors / delamp | $392 | $875 |
$144
4,689
kWh
|
$248
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $248 | $500 |
$49
1,465
kWh
|
$22
-
kW-mo/yr
|
- | - | $177 | |
| 09 | 2.7135: Install occupancy sensors | $65 | $200 |
$65
2,052
kWh
|
- | - | - | - | |
| 10 | 2.6218: Turn off equipment when not in use | $21 | $53 |
$21
586
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $12,728 | $19,878 |
$2,182
70,632
kWh
|
$1,262
-
kW-mo/yr
|
$6,319
-
MMBtu
|
$2,788 | $177 | ||
| TOTAL IMPLEMENTED | $1,118 | $2,750 |
$1,118
36,342
kWh
|
- | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs