ITAC Assessment: ND0285
ITAC logo
ITAC Assessment: ND0285
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Aircraft sheet metal assemblies
NAICS
n/a
SIC 3444: Sheet Metal Work
Sales Range $5
M
to 10
M
# of Employees 80
Plant Area 120,000
ft2
Annual Production 150,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $261,886 5,387,163
kWh
Electricity Demand $98,628 9,584
kW-mo/yr
Natural Gas $74,658 13,682
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $51,339 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Administrative Changes Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $37,542 $3,781 n/a - - $37,542
-
MMBtu
- -
02 4.122: Develop standard procedures to improve internal yields $8,300 $6,000 n/a - - - - $8,300
03 3.5313: Increase amount of waste recovered for resale $1,532 $1,000 n/a - - - $1,532
-
gal
-
04 2.4133: Use most efficient type of electric motors $1,543 $8,240 n/a $1,543
30,481
kWh
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $588 $440 n/a $290
2,638
kWh
$298
-
kW-mo/yr
- - -
06 2.2514: Cover open tanks $568 $55 n/a - - $568
-
MMBtu
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $564 $1,051 n/a $278
12,016
kWh
$286
-
kW-mo/yr
- - -
08 2.4221: Install compressor air intakes in coolest locations $226 $260 n/a $226
4,396
kWh
- - - -
09 2.7135: Install occupancy sensors $189 $600 n/a $189
4,103
kWh
- - - -
10 2.7447: Install vinyl strip / high speed / air curtain doors $137 $163 n/a - - $137
-
MMBtu
- -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $118 $220 n/a $118
2,345
kWh
- - - -
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $26 $20 n/a $26
586
kWh
- - - -
13 2.6218: Turn off equipment when not in use $6 $20 n/a $6
293
kWh
- - - -
TOTAL RECOMMENDED $51,339 $21,850 $2,676
56,858
kWh
$584
-
kW-mo/yr
$38,247
-
MMBtu
$1,532
-
gal
$8,300
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs