ITAC Assessment: ND0284
ITAC logo
ITAC Assessment: ND0284
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Aero-Space and Land-Based Turbines
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 74
Plant Area 59,000
ft2
Annual Production 20,000,000
lb
Production Hrs. Annual 5,200
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,087 1,126,612
kWh
Electricity Demand $30,623 2,936
kW-mo/yr
Natural Gas $9,308 2,025
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,766 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.3212: Optimize plant power factor $10,790 $6,000 n/a - - - $10,790 -
02 2.7447: Install vinyl strip / high speed / air curtain doors $9,415 $18,234 n/a - - $9,415
-
MMBtu
- -
03 2.4133: Use most efficient type of electric motors $8,231 $16,400 n/a $5,421
140,387
kWh
$2,810
-
kW-mo/yr
- - -
04 2.7447: Install vinyl strip / high speed / air curtain doors $1,848 $545 n/a - - $1,848
-
MMBtu
- -
05 2.2531: Re-size charging openings or add movable cover or door $1,756 $2,600 n/a - - $1,756
-
MMBtu
- -
06 2.7135: Install occupancy sensors $1,504 $1,800 n/a $803
25,498
kWh
$701
-
kW-mo/yr
- - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,494 $1,310 n/a $807
25,498
kWh
$687
-
kW-mo/yr
- - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $829 $220 n/a $829
20,809
kWh
- - - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $693 $810 n/a $502
11,723
kWh
$191
-
kW-mo/yr
- - -
10 2.2437: Recover waste heat from equipment $608 $545 n/a - - $608
-
MMBtu
- -
11 3.1191: Change procedures / equipment / operating conditions $381 $360 n/a - - - - $381
12 2.4221: Install compressor air intakes in coolest locations $184 $200 n/a $184
3,224
kWh
- - - -
13 2.6218: Turn off equipment when not in use $17 $47 n/a $10
586
kWh
$7
-
kW-mo/yr
- - -
14 2.7122: Disconnect ballasts $16 $60 n/a $9
586
kWh
$7
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $37,766 $49,131 $8,565
228,311
kWh
$4,403
-
kW-mo/yr
$13,627
-
MMBtu
$10,790 $381
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs