| Assessment Year | 1997 |
|---|---|
| Principal Product | Aero-Space and Land-Based Turbines |
| NAICS |
n/a
|
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 74 |
| Plant Area |
59,000
ft2
|
| Annual Production | 20,000,000
lb
|
| Production Hrs. Annual | 5,200
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $31,087 | 1,126,612 |
kWh
|
$0.028 |
| Electricity Demand | $30,623 | 2,936 |
kW-mo/yr
|
$10.43 |
| Natural Gas | $9,308 | 2,025 |
MMBtu
|
$4.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $37,766 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $10,790 | $6,000 | n/a | - | - | - | $10,790 | - |
| 02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $9,415 | $18,234 | n/a | - | - |
$9,415
-
MMBtu
|
- | - |
| 03 | 2.4133: Use most efficient type of electric motors | $8,231 | $16,400 | n/a |
$5,421
140,387
kWh
|
$2,810
-
kW-mo/yr
|
- | - | - |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,848 | $545 | n/a | - | - |
$1,848
-
MMBtu
|
- | - |
| 05 | 2.2531: Re-size charging openings or add movable cover or door | $1,756 | $2,600 | n/a | - | - |
$1,756
-
MMBtu
|
- | - |
| 06 | 2.7135: Install occupancy sensors | $1,504 | $1,800 | n/a |
$803
25,498
kWh
|
$701
-
kW-mo/yr
|
- | - | - |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,494 | $1,310 | n/a |
$807
25,498
kWh
|
$687
-
kW-mo/yr
|
- | - | - |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $829 | $220 | n/a |
$829
20,809
kWh
|
- | - | - | - |
| 09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $693 | $810 | n/a |
$502
11,723
kWh
|
$191
-
kW-mo/yr
|
- | - | - |
| 10 | 2.2437: Recover waste heat from equipment | $608 | $545 | n/a | - | - |
$608
-
MMBtu
|
- | - |
| 11 | 3.1191: Change procedures / equipment / operating conditions | $381 | $360 | n/a | - | - | - | - | $381 |
| 12 | 2.4221: Install compressor air intakes in coolest locations | $184 | $200 | n/a |
$184
3,224
kWh
|
- | - | - | - |
| 13 | 2.6218: Turn off equipment when not in use | $17 | $47 | n/a |
$10
586
kWh
|
$7
-
kW-mo/yr
|
- | - | - |
| 14 | 2.7122: Disconnect ballasts | $16 | $60 | n/a |
$9
586
kWh
|
$7
-
kW-mo/yr
|
- | - | - |
| TOTAL RECOMMENDED | $37,766 | $49,131 |
$8,565
228,311
kWh
|
$4,403
-
kW-mo/yr
|
$13,627
-
MMBtu
|
$10,790 | $381 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs