ITAC Assessment: ND0283
ITAC logo
ITAC Assessment: ND0283
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product jet engine components
NAICS
n/a
SIC 3498: Fabricated Pipe and Pipe Fittings
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 36,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 4,800
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $49,690 2,220,399
kWh
Electricity Demand $81,272 7,205
kW-mo/yr
Natural Gas $11,733 2,067
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,422 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $4,836 $5,760 - - - - - - $4,836
02 3.4111: Use closed cycle process to minimize waste water production $2,430 $18,000 - - - $2,430
-
Tgal
- - -
03 2.4133: Use most efficient type of electric motors $2,026 $6,660 $787
35,170
kWh
$1,239
-
kW-mo/yr
- - - - -
04 2.7135: Install occupancy sensors $692 $400 $499
22,274
kWh
$193
-
kW-mo/yr
- - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $844 $692 $322
14,361
kWh
$522
-
kW-mo/yr
- - - - -
06 2.2511: Insulate bare equipment $788 $192 $788
40,739
kWh
- - - - - -
07 3.6192: Use a less expensive method of waste removal $625 $275 - - - - $625
-
lb
- -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $563 $300 $216
9,672
kWh
$347
-
kW-mo/yr
- - - - -
09 2.2437: Recover waste heat from equipment $543 $550 - - $543
-
MMBtu
- - - -
10 2.4221: Install compressor air intakes in coolest locations $316 $240 $125
5,569
kWh
$191
-
kW-mo/yr
- - - - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $279 $32 $98
4,396
kWh
$181
-
kW-mo/yr
- - - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $256 $400 $46
2,052
kWh
$68
-
kW-mo/yr
- - - $142 -
13 2.8221: Consider intermediate or economy size autos / trucks $156 - - - - - - - $156
14 2.7491: Insulate glazing, walls, ceilings, and roofs $68 $48 - - $68
-
MMBtu
- - - -
TOTAL RECOMMENDED $14,422 $33,549 $2,881
134,233
kWh
$2,741
-
kW-mo/yr
$611
-
MMBtu
$2,430
-
Tgal
$625
-
lb
$142 $4,992
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs