| Assessment Year | 1997 |
|---|---|
| Principal Product | jet engine components |
| NAICS |
n/a
|
| SIC | 3498: Fabricated Pipe and Pipe Fittings |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
36,000
ft2
|
| Annual Production | 100,000
pieces
|
| Production Hrs. Annual | 4,800
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $49,690 | 2,220,399 |
kWh
|
$0.022 |
| Electricity Demand | $81,272 | 7,205 |
kW-mo/yr
|
$11.28 |
| Natural Gas | $11,733 | 2,067 |
MMBtu
|
$5.68 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,422 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $4,836 | $5,760 | - | - | - | - | - | - | $4,836 | |
| 02 | 3.4111: Use closed cycle process to minimize waste water production | $2,430 | $18,000 | - | - | - |
$2,430
-
Tgal
|
- | - | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $2,026 | $6,660 |
$787
35,170
kWh
|
$1,239
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.7135: Install occupancy sensors | $692 | $400 |
$499
22,274
kWh
|
$193
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $844 | $692 |
$322
14,361
kWh
|
$522
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 2.2511: Insulate bare equipment | $788 | $192 |
$788
40,739
kWh
|
- | - | - | - | - | - | |
| 07 | 3.6192: Use a less expensive method of waste removal | $625 | $275 | - | - | - | - |
$625
-
lb
|
- | - | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $563 | $300 |
$216
9,672
kWh
|
$347
-
kW-mo/yr
|
- | - | - | - | - | |
| 09 | 2.2437: Recover waste heat from equipment | $543 | $550 | - | - |
$543
-
MMBtu
|
- | - | - | - | |
| 10 | 2.4221: Install compressor air intakes in coolest locations | $316 | $240 |
$125
5,569
kWh
|
$191
-
kW-mo/yr
|
- | - | - | - | - | |
| 11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $279 | $32 |
$98
4,396
kWh
|
$181
-
kW-mo/yr
|
- | - | - | - | - | |
| 12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $256 | $400 |
$46
2,052
kWh
|
$68
-
kW-mo/yr
|
- | - | - | $142 | - | |
| 13 | 2.8221: Consider intermediate or economy size autos / trucks | $156 | - | - | - | - | - | - | - | $156 | |
| 14 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $68 | $48 | - | - |
$68
-
MMBtu
|
- | - | - | - | |
| TOTAL RECOMMENDED | $14,422 | $33,549 |
$2,881
134,233
kWh
|
$2,741
-
kW-mo/yr
|
$611
-
MMBtu
|
$2,430
-
Tgal
|
$625
-
lb
|
$142 | $4,992 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs