Assessment Year | 1997 |
---|---|
Principal Product | jet engine components |
NAICS |
n/a
|
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
36,000
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 4,800
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $49,690 | 2,220,399 |
kWh
|
$0.022 |
Electricity Demand | $81,272 | 7,205 |
kW-mo/yr
|
$11.28 |
Natural Gas | $11,733 | 2,067 |
MMBtu
|
$5.68 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,422 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $4,836 | $5,760 | - | - | - | - | - | - | $4,836 | |
02 | 3.4111: Use closed cycle process to minimize waste water production | $2,430 | $18,000 | - | - | - |
$2,430
-
Tgal
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $2,026 | $6,660 |
$787
35,170
kWh
|
$1,239
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7135: Install occupancy sensors | $692 | $400 |
$499
22,274
kWh
|
$193
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $844 | $692 |
$322
14,361
kWh
|
$522
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.2511: Insulate bare equipment | $788 | $192 |
$788
40,739
kWh
|
- | - | - | - | - | - | |
07 | 3.6192: Use a less expensive method of waste removal | $625 | $275 | - | - | - | - |
$625
-
lb
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $563 | $300 |
$216
9,672
kWh
|
$347
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 2.2437: Recover waste heat from equipment | $543 | $550 | - | - |
$543
-
MMBtu
|
- | - | - | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $316 | $240 |
$125
5,569
kWh
|
$191
-
kW-mo/yr
|
- | - | - | - | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $279 | $32 |
$98
4,396
kWh
|
$181
-
kW-mo/yr
|
- | - | - | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $256 | $400 |
$46
2,052
kWh
|
$68
-
kW-mo/yr
|
- | - | - | $142 | - | |
13 | 2.8221: Consider intermediate or economy size autos / trucks | $156 | - | - | - | - | - | - | - | $156 | |
14 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $68 | $48 | - | - |
$68
-
MMBtu
|
- | - | - | - | |
TOTAL RECOMMENDED | $14,422 | $33,549 |
$2,881
134,233
kWh
|
$2,741
-
kW-mo/yr
|
$611
-
MMBtu
|
$2,430
-
Tgal
|
$625
-
lb
|
$142 | $4,992 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs