ITAC Assessment: ND0281
ITAC logo
ITAC Assessment: ND0281
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Automotive Trailers
NAICS
n/a
SIC 3798:
Sales Range $10
M
to 50
M
# of Employees 240
Plant Area 140,510
ft2
Annual Production 6,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,882 1,119,871
kWh
Electricity Demand $28,237 5,011
kW-mo/yr
Natural Gas $66,454 16,497
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,874 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,129

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $221 $260 $221
4,689
kWh
- - - - -
02 2.4221: Install compressor air intakes in coolest locations $413 $500 $290
6,155
kWh
$123
-
kW-mo/yr
- - - -
03 2.2437: Recover waste heat from equipment $307 $300 - - - $307
-
MMBtu
- -
04 2.4133: Use most efficient type of electric motors $1,495 $5,670 $1,273
26,964
kWh
$222
-
kW-mo/yr
- - - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $37 $50 $37
586
kWh
- - - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,074 $1,620 $706
14,947
kWh
$368
-
kW-mo/yr
- - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $365 $601 $238
4,982
kWh
$127
-
kW-mo/yr
- - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $706 $3,150 $457
9,672
kWh
$249
-
kW-mo/yr
- - - -
09 2.6218: Turn off equipment when not in use $152 - $152
2,052
kWh
- - - - -
10 2.7447: Install vinyl strip / high speed / air curtain doors $23 $60 - - - $23
-
MMBtu
- -
11 2.7492: Use proper thickness of insulation on building envelope $1,957 $500 - - - $1,957
-
MMBtu
- -
12 3.8221: Use alternatives for acids / alkaline (water, steam, abrasive) $423 $50 - - - - $423
-
gal
-
13 2.8112: Combine utility meters $2,802 $1,710 - - $2,802 - - -
14 2.8122: Use utility controlled power management $2,489 $800 - - $2,489 - - -
15 4.513: Re-arrange equipment layout to reduce labor costs $6,410 $100 $170
2,345
kWh
- - - - $6,240
TOTAL RECOMMENDED $18,874 $15,371 $3,544
72,392
kWh
$1,089
-
kW-mo/yr
$5,291 $2,287
-
MMBtu
$423
-
gal
$6,240
TOTAL IMPLEMENTED $2,129 $6,430 $1,784
37,808
kWh
$345
-
kW-mo/yr
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs