Assessment Year | 1997 |
---|---|
Principal Product | Automotive Trailers |
NAICS |
n/a
|
SIC | 3798: |
Sales Range | $10 M to 50M |
# of Employees | 240 |
Plant Area |
140,510
ft2
|
Annual Production | 6,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $52,882 | 1,119,871 |
kWh
|
$0.047 |
Electricity Demand | $28,237 | 5,011 |
kW-mo/yr
|
$5.64 |
Natural Gas | $66,454 | 16,497 |
MMBtu
|
$4.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,874 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,129 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $221 | $260 |
$221
4,689
kWh
|
- | - | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $413 | $500 |
$290
6,155
kWh
|
$123
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.2437: Recover waste heat from equipment | $307 | $300 | - | - | - |
$307
-
MMBtu
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $1,495 | $5,670 |
$1,273
26,964
kWh
|
$222
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $37 | $50 |
$37
586
kWh
|
- | - | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,074 | $1,620 |
$706
14,947
kWh
|
$368
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $365 | $601 |
$238
4,982
kWh
|
$127
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $706 | $3,150 |
$457
9,672
kWh
|
$249
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.6218: Turn off equipment when not in use | $152 | - |
$152
2,052
kWh
|
- | - | - | - | - | |
10 | 2.7447: Install vinyl strip / high speed / air curtain doors | $23 | $60 | - | - | - |
$23
-
MMBtu
|
- | - | |
11 | 2.7492: Use proper thickness of insulation on building envelope | $1,957 | $500 | - | - | - |
$1,957
-
MMBtu
|
- | - | |
12 | 3.8221: Use alternatives for acids / alkaline (water, steam, abrasive) | $423 | $50 | - | - | - | - |
$423
-
gal
|
- | |
13 | 2.8112: Combine utility meters | $2,802 | $1,710 | - | - | $2,802 | - | - | - | |
14 | 2.8122: Use utility controlled power management | $2,489 | $800 | - | - | $2,489 | - | - | - | |
15 | 4.513: Re-arrange equipment layout to reduce labor costs | $6,410 | $100 |
$170
2,345
kWh
|
- | - | - | - | $6,240 | |
TOTAL RECOMMENDED | $18,874 | $15,371 |
$3,544
72,392
kWh
|
$1,089
-
kW-mo/yr
|
$5,291 |
$2,287
-
MMBtu
|
$423
-
gal
|
$6,240 | ||
TOTAL IMPLEMENTED | $2,129 | $6,430 |
$1,784
37,808
kWh
|
$345
-
kW-mo/yr
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs