ITAC Assessment: ND0278
ITAC logo
ITAC Assessment: ND0278
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Machined automotive parts
NAICS
n/a
SIC 3463: Nonferrous Forgings
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 75,000
ft2
Annual Production 35,000,000
pieces
Production Hrs. Annual 6,428
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $265,320 7,792,497
kWh
Electricity Demand $170,255 14,905
kW-mo/yr
Natural Gas $8,851 2,100
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,545 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,354

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $209 $754 $151
4,396
kWh
$58
-
kW-mo/yr
- - - - - - -
02 2.7131: Add area lighting switches $327 $200 $327
9,672
kWh
- - - - - - - -
03 2.7135: Install occupancy sensors $129 $400 $129
3,810
kWh
- - - - - - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $196 $450 $160
3,224
kWh
$36
-
kW-mo/yr
- - - - - - -
05 2.4221: Install compressor air intakes in coolest locations $2,214 $300 $2,214
62,427
kWh
- - - - - - - -
06 2.2437: Recover waste heat from equipment $3,651 $1,560 - - - $3,651
-
MMBtu
- - - - -
07 2.7447: Install vinyl strip / high speed / air curtain doors $195 $260 - - - $195
-
MMBtu
- - - - -
08 2.4133: Use most efficient type of electric motors $4,578 $2,925 $2,924
89,390
kWh
$1,654
-
kW-mo/yr
- - - - - - -
09 2.3212: Optimize plant power factor $778 $1,268 - - $778 - - - - - -
10 2.7447: Install vinyl strip / high speed / air curtain doors $566 $394 - - - $566
-
MMBtu
- - - - -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $242 $200 $242
7,034
kWh
- - - - - - - -
12 2.6218: Turn off equipment when not in use $20 - $20
586
kWh
- - - - - - - -
13 3.5316: Contract a wood pallet recycling company $396 - - - - - - - $396
-
lb
- -
14 3.1191: Change procedures / equipment / operating conditions $73 $90 - - - - - - - $73 -
15 3.6125: Sell combustible waste $4,950 $1,000 - - - - - $4,950
-
gal
- - -
16 4.311: Schedule deliveries according to demand $461 - - - - - - - - - $461
17 3.1191: Change procedures / equipment / operating conditions $2,628 $720 - - - - - - - $2,628 -
18 3.5315: Lease / purchase baler; sell cardboard to recycler $2,160 $480 - - - - - - $2,160
-
lb
- -
19 3.8221: Use alternatives for acids / alkaline (water, steam, abrasive) $920 - - - - - - $920
-
gal
- - -
20 3.7393: Implement a machine and coolant sump cleaning program to minimize coolant contamination $852 $3,000 - - - - $852
-
Tgal
- - - -
TOTAL RECOMMENDED $25,545 $14,001 $6,167
180,539
kWh
$1,748
-
kW-mo/yr
$778 $4,412
-
MMBtu
$852
-
Tgal
$5,870
-
gal
$2,556
-
lb
$2,701 $461
TOTAL IMPLEMENTED $11,354 $8,529 $3,804
113,716
kWh
$1,748
-
kW-mo/yr
- - $852
-
Tgal
$4,950
-
gal
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs