| Assessment Year | 1997 |
|---|---|
| Principal Product | Machine Forgings |
| NAICS |
n/a
|
| SIC | 3462: Iron and Steel Forgings |
| Sales Range | $10 M to 50M |
| # of Employees | 138 |
| Plant Area |
90,000
ft2
|
| Annual Production | 3,200,000
pieces
|
| Production Hrs. Annual | 6,560
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $323,785 | 6,342,907 |
kWh
|
$0.051 |
| Electricity Demand | $130,778 | 13,389 |
kW-mo/yr
|
$9.77 |
| Natural Gas | $109,191 | 21,349 |
MMBtu
|
$5.11 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,783 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $28,783 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $9,097 | $1,655 |
$6,459
126,905
kWh
|
$2,638
-
kW-mo/yr
|
- | |
| 02 | 2.3212: Optimize plant power factor | $10,153 | $15,462 | - |
$10,153
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,526 | $240 |
$4,633
91,149
kWh
|
$1,893
-
kW-mo/yr
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $2,078 | $1,500 |
$1,475
29,015
kWh
|
$603
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $460 | $650 |
$327
3,224
kWh
|
$133
-
kW-mo/yr
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $297 | $144 |
$211
4,103
kWh
|
$86
-
kW-mo/yr
|
- | |
| 07 | 2.7444: Close holes and openings in building such as broken windows | $172 | $449 | - | - |
$172
-
MMBtu
|
|
| TOTAL RECOMMENDED | $28,783 | $20,100 |
$13,105
254,396
kWh
|
$15,506
-
kW-mo/yr
|
$172
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $28,783 | $20,100 |
$13,105
254,396
kWh
|
$15,506
-
kW-mo/yr
|
$172
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs