Assessment Year | 1997 |
---|---|
Principal Product | Machined Auto Parts |
NAICS |
n/a
|
SIC | 3514: |
Sales Range | $50 M to 100M |
# of Employees | 288 |
Plant Area |
100,000
ft2
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 7,956
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $384,450 | 7,846,718 |
kWh
|
$0.049 |
Electricity Demand | $220,188 | 20,640 |
kW-mo/yr
|
$10.67 |
Natural Gas | $50,840 | 10,721 |
MMBtu
|
$4.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $68,696 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $68,696 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $98 | $74 |
$39
1,465
kWh
|
$59
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $288 | $800 |
$115
3,810
kWh
|
$173
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $134 | $600 |
$134
4,396
kWh
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $2,755 | $500 |
$2,755
91,442
kWh
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $806 | $400 | - | - |
$806
-
MMBtu
|
|
06 | 2.7444: Close holes and openings in building such as broken windows | $153 | $133 | - | - |
$153
-
MMBtu
|
|
07 | 2.4133: Use most efficient type of electric motors | $15,578 | $5,195 |
$6,231
137,749
kWh
|
$9,347
-
kW-mo/yr
|
- | |
08 | 2.8114: Change rate schedules or other changes in utility service | $40,340 | $7,000 | - |
$40,340
-
kW-mo/yr
|
- | |
09 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $8,544 | $8,000 | - |
$8,544
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $68,696 | $22,702 |
$9,274
238,862
kWh
|
$58,463
-
kW-mo/yr
|
$959
-
MMBtu
|
||
TOTAL IMPLEMENTED | $68,696 | $22,702 |
$9,274
238,862
kWh
|
$58,463
-
kW-mo/yr
|
$959
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs