ITAC Assessment: ND0257
ITAC logo
ITAC Assessment: ND0257
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Corrugated Cardboard
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 205,000
ft2
Annual Production 192,000
thousand feet
Production Hrs. Annual 4,000
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $79,330 2,055,979
kWh
Electricity Demand $61,790 5,352
kW-mo/yr
Natural Gas $25,826 5,901
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,408 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,092

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.4221: Install compressor air intakes in coolest locations $68 $200 $68
3,224
kWh
- - -
02 2.4133: Use most efficient type of electric motors $7,053 $8,690 $3,963
102,579
kWh
$3,090
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $179 $297 $101
2,638
kWh
$78
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $344 $750 $193
4,982
kWh
$151
-
kW-mo/yr
- -
05 2.6218: Turn off equipment when not in use $164 $1,344 $164
7,620
kWh
- - -
06 2.7447: Install vinyl strip / high speed / air curtain doors $4,584 $725 - - $4,584
-
MMBtu
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,666 $585 $936
24,326
kWh
$730
-
kW-mo/yr
- -
08 3.5316: Contract a wood pallet recycling company $1,350 - - - - $1,350
-
lb
TOTAL RECOMMENDED $15,408 $12,591 $5,425
145,369
kWh
$4,049
-
kW-mo/yr
$4,584
-
MMBtu
$1,350
-
lb
TOTAL IMPLEMENTED $5,092 $2,819 $357
12,602
kWh
$151
-
kW-mo/yr
$4,584
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs