| Assessment Year | 1995 |
|---|---|
| Principal Product | Wirebound produce boxes |
| NAICS |
n/a
|
| SIC | 2449: Wood Containers, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 200 |
| Plant Area |
150,000
ft2
|
| Annual Production | 8,000,000
pieces
|
| Production Hrs. Annual | 2,200
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $98,023 | 1,361,958 |
kWh
|
$0.072 |
| Natural Gas | $28,077 | 5,536 |
MMBtu
|
$5.07 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $138,931 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $138,485 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $776 | $480 |
$776
9,965
kWh
|
- | - | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $740 | $95 |
$740
9,379
kWh
|
- | - | - | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $446 | $600 | - |
$446
-
MMBtu
|
- | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $2,719 | $5,310 |
$2,719
31,946
kWh
|
- | - | - | |
| 05 | 2.8211: Consolidate freight shipments and/or deliveries | $93,750 | $100,000 | - | - | - | $93,750 | |
| 06 | 2.1116: Improve combustion control capability | $40,500 | $35,000 | - | - |
$40,500
-
lb
|
- | |
| TOTAL RECOMMENDED | $138,931 | $141,485 |
$4,235
51,290
kWh
|
$446
-
MMBtu
|
$40,500
-
lb
|
$93,750 | ||
| TOTAL IMPLEMENTED | $138,485 | $140,885 |
$4,235
51,290
kWh
|
- |
$40,500
-
lb
|
$93,750 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs