| Assessment Year | 1996 |
|---|---|
| Principal Product | Auto Ignition Wire |
| NAICS |
n/a
|
| SIC | 3694: Electrical Equipment for Internal Combustion Engines |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
60,000
ft2
|
| Annual Production | 5,000,000
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $59,018 | 1,405,334 |
kWh
|
$0.042 |
| Electricity Demand | $35,858 | 3,835 |
kW-mo/yr
|
$9.35 |
| Electricity Fees | $15,152 | - |
|
- |
| Natural Gas | $17,893 | 3,893 |
MMBtu
|
$4.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,497 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,594 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $345 | $640 |
$186
4,103
kWh
|
$159
-
kW-mo/yr
|
- | - | |
| 02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $290 | $900 | - | - | - |
$290
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,365 | $556 |
$1,495
33,998
kWh
|
$870
-
kW-mo/yr
|
- | - | |
| 04 | 2.6218: Turn off equipment when not in use | $564 | $100 |
$564
12,896
kWh
|
- | - | - | |
| 05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $169 | $400 |
$(-14.0)
(-879)
kWh
|
$75
-
kW-mo/yr
|
$108 | - | |
| 06 | 2.6121: Reduce hot water temperature to the minimum required | $41 | - |
$41
879
kWh
|
- | - | - | |
| 07 | 2.4133: Use most efficient type of electric motors | $4,889 | $10,440 |
$3,094
70,340
kWh
|
$1,795
-
kW-mo/yr
|
- | - | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $855 | $1,120 |
$541
12,309
kWh
|
$314
-
kW-mo/yr
|
- | - | |
| 09 | 2.3212: Optimize plant power factor | $265 | $192 | - | - | $265 | - | |
| 10 | 2.4221: Install compressor air intakes in coolest locations | $518 | $250 |
$518
11,723
kWh
|
- | - | - | |
| 11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,180 | $800 |
$7,180
163,247
kWh
|
- | - | - | |
| 12 | 2.2437: Recover waste heat from equipment | $496 | $700 | - | - | - |
$496
-
MMBtu
|
|
| 13 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $10,520 | $30,000 | - | - | $10,520 | - | |
| TOTAL RECOMMENDED | $28,497 | $46,098 |
$13,605
308,616
kWh
|
$3,213
-
kW-mo/yr
|
$10,893 |
$786
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $15,594 | $12,988 |
$12,374
281,360
kWh
|
$2,665
-
kW-mo/yr
|
$265 |
$290
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs