Assessment Year | 1988 |
---|---|
Principal Product | DENIM JEANS |
NAICS |
n/a
|
SIC | 2325: Men's and Boys' Separate Trousers and Slacks |
Sales Range | $50 M to 100M |
# of Employees | 525 |
Plant Area |
n/a
|
Annual Production | 6,000,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $304,190 | 6,439,918 |
kWh
|
$0.047 |
Natural Gas | $113,366 | 27,217 |
MMBtu
|
$4.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $46,825 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,235 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $589 | $340 | - |
$589
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,675 | $37,500 |
$20,145
443,728
kWh
|
- | $4,530 | |
03 | 2.7261: Install timers and/or thermostats | $5,646 | $900 | - |
$5,646
-
MMBtu
|
- | |
04 | 2.2437: Recover waste heat from equipment | $2,333 | $1,490 | - |
$2,333
-
MMBtu
|
- | |
05 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $5,873 | - |
$5,873
135,991
kWh
|
- | - | |
06 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $7,709 | $6,300 |
$7,709
177,902
kWh
|
- | - | |
TOTAL RECOMMENDED | $46,825 | $46,530 |
$33,727
757,621
kWh
|
$8,568
-
MMBtu
|
$4,530 | ||
TOTAL IMPLEMENTED | $6,235 | $1,240 | - |
$6,235
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs