Assessment Year | 1995 |
---|---|
Principal Product | paints, resins, varnishes |
NAICS |
n/a
|
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
83,000
ft2
|
Annual Production | 1,200
Tgal
|
Production Hrs. Annual | 8,740
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $87,649 | 1,508,793 |
kWh
|
$0.058 |
Natural Gas | $71,369 | 15,760 |
MMBtu
|
$4.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,453 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,107 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $645 | $200 |
$645
11,430
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,862 | $295 |
$1,862
33,118
kWh
|
- | |
03 | 2.1213: Direct warmest air to combustion intake | $1,653 | $1,500 | - |
$1,653
-
MMBtu
|
|
04 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $70 | $92 | - |
$70
-
MMBtu
|
|
05 | 2.4133: Use most efficient type of electric motors | $13,304 | $11,130 |
$13,304
296,893
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $786 | $828 |
$786
11,137
kWh
|
- | |
07 | 2.8112: Combine utility meters | $3,325 | $3,325 |
$3,325
-
kWh
|
- | |
08 | 2.3212: Optimize plant power factor | $5,298 | $3,780 |
$5,298
-
kWh
|
- | |
09 | 2.7447: Install vinyl strip / high speed / air curtain doors | $276 | $335 | - |
$276
-
MMBtu
|
|
10 | 2.6218: Turn off equipment when not in use | $614 | - |
$614
7,620
kWh
|
- | |
11 | 2.2437: Recover waste heat from equipment | $620 | $500 | - |
$620
-
MMBtu
|
|
TOTAL RECOMMENDED | $28,453 | $21,985 |
$25,834
360,198
kWh
|
$2,619
-
MMBtu
|
||
TOTAL IMPLEMENTED | $18,107 | $13,288 |
$17,211
360,198
kWh
|
$896
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs