| Assessment Year | 1994 |
|---|---|
| Principal Product | Progressive Dies |
| NAICS |
n/a
|
| SIC | 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds |
| Sales Range | $5 M to 10M |
| # of Employees | 66 |
| Plant Area |
77,000
ft2
|
| Annual Production | 60
pieces
|
| Production Hrs. Annual | 5,151
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $79,091 | 1,423,798 |
kWh
|
$0.056 |
| Natural Gas | $11,608 | 2,019 |
MMBtu
|
$5.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $15,977 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,457 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $7,378 | $1,000 |
$7,378
103,165
kWh
|
|
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $3,596 | $200 |
$3,596
49,531
kWh
|
|
| 03 | 2.4133: Use most efficient type of electric motors | $2,553 | $3,020 |
$2,553
37,222
kWh
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $601 | $500 |
$601
9,965
kWh
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $495 | $504 |
$495
9,379
kWh
|
|
| 06 | 2.7124: Make a practice of turning off lights when not needed | $361 | - |
$361
7,034
kWh
|
|
| 07 | 2.6231: Utilize controls to operate equipment only when needed | $308 | $630 |
$308
5,569
kWh
|
|
| 08 | 2.4221: Install compressor air intakes in coolest locations | $275 | $400 |
$275
4,396
kWh
|
|
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $232 | $640 |
$232
4,103
kWh
|
|
| 10 | 2.6231: Utilize controls to operate equipment only when needed | $178 | $260 |
$178
3,517
kWh
|
|
| TOTAL RECOMMENDED | $15,977 | $7,154 |
$15,977
233,881
kWh
|
||
| TOTAL IMPLEMENTED | $1,457 | $1,004 |
$1,457
26,378
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs