ITAC Assessment: ND0007
ITAC logo
ITAC Assessment: ND0007
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product ALUMINUM EXTRUSIONS
NAICS
n/a
SIC 3354: Aluminum Extruded Products
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area
n/a
Annual Production 13,000,000
lb
Production Hrs. Annual 6,864
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $154,564 3,113,130
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,401 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,401

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $907 $1,315 $907
18,171
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,404 - $451
9,086
kWh
$953
03 2.4221: Install compressor air intakes in coolest locations $611 $500 $611
12,309
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $57 - $131
2,638
kWh
$(-74.0)
05 2.6232: Install set-back timers $233 $250 $233
4,689
kWh
-
06 2.7111: Reduce illumination to minimum necessary levels $189 $30 $189
3,810
kWh
-
TOTAL RECOMMENDED $3,401 $2,095 $2,522
50,703
kWh
$879
TOTAL IMPLEMENTED $3,401 $2,095 $2,522
50,703
kWh
$879
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs