| Assessment Year | 1989 |
|---|---|
| Principal Product | TRUCK & VAN BODIES |
| NAICS |
n/a
|
| SIC | 3731: Ship Building and Repairing |
| Sales Range | $10 M to 50M |
| # of Employees | 96 |
| Plant Area |
n/a
|
| Annual Production | 2,400
pieces
|
| Production Hrs. Annual | 4,027
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $48,410 | 766,413 |
kWh
|
$0.063 |
| Natural Gas | $35,312 | 6,933 |
MMBtu
|
$5.09 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,550 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,758 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $6,260 | $1,800 | - |
$6,260
-
MMBtu
|
|
| 02 | 2.2532: Use only amount of air necessary to prevent explosion hazard | $3,041 | $231 |
$703
11,137
kWh
|
$2,338
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,289 | $1,193 |
$1,289
20,223
kWh
|
- | |
| 04 | 2.1123: Install automatic stack damper | $2,209 | $1,200 | - |
$2,209
-
MMBtu
|
|
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $1,751 | $4,000 | - |
$1,751
-
MMBtu
|
|
| TOTAL RECOMMENDED | $14,550 | $8,424 |
$1,992
31,360
kWh
|
$12,558
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $9,758 | $4,193 |
$1,289
20,223
kWh
|
$8,469
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs