Assessment Year | 2018 |
---|---|
Principal Product | Chemicals |
NAICS | 325199: All Other Basic Organic Chemical Manufacturing |
SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
45,000
ft2
|
Annual Production | 10,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $53,840 | 986,988 |
kWh
|
$0.055 | |
Electricity Demand | $16,051 | 2,067 |
kW-mo/yr
|
$7.77 | |
Natural Gas | $33,838 | 5,402 |
MMBtu
|
$6.26 | |
Waste Disposal Costs | |||||
Water Usage | $12,150 | 1,500 |
Tgal
|
$8.10 | |
Water Disposal | $18,150 | 1,500 |
Tgal
|
$12.10 | |
TOTAL YEARLY COSTS | $134,029 | ||||
RECOMMENDED SAVINGS* | $256,014 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2615: Clean condenser tubes | $226,480 | $50,000 | - | - | - | $(-30,000.0) | $256,480 | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $909 | $750 |
$708
12,960
kWh
|
$201
-
kW-mo/yr
|
- | - | - | |
03 | 2.4154: Avoid rewinding motors more than twice | $2,752 | $5,685 |
$2,143
39,257
kWh
|
$609
-
kW-mo/yr
|
- | - | - | |
04 | 3.4116: Meter recycled water (to reduce sewer charges) | $12,341 | $2,450 | - | - |
$12,461
-
Tgal
|
$(-120.0) | - | |
05 | 2.4226: Use / purchase optimum sized compressor | $10,360 | - |
$8,063
147,676
kWh
|
$2,297
-
kW-mo/yr
|
- | - | - | |
06 | 2.8114: Change rate schedules or other changes in utility service | $3,172 | $500 |
$3,172
-
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $256,014 | $59,385 |
$14,086
199,893
kWh
|
$3,107
-
kW-mo/yr
|
$12,461
-
Tgal
|
$(-30,120.0) | $256,480 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Ancillary Material Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs