Assessment Year | 2016 |
---|---|
Principal Product | Conveyor belts |
NAICS | 326220: Rubber and Plastics Hoses and Belting Manufacturing |
SIC | 3052: Rubber and Plastics Hose and Belting |
Sales Range | $10 M to 50M |
# of Employees | 39 |
Plant Area |
117,500
ft2
|
Annual Production | 800,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $166,255 | 2,999,054 |
kWh
|
$0.055 |
Electricity Demand | $99,309 | 11,944 |
kW-mo/yr
|
$8.31 |
Natural Gas | $122,390 | 16,248 |
MMBtu
|
$7.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $74,209 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $8,449 | $20,000 | - | - |
$8,449
-
MMBtu
|
- | - | |
02 | 2.6218: Turn off equipment when not in use | $512 | $450 |
$42
750
kWh
|
$266
-
kW-mo/yr
|
$204
-
MMBtu
|
- | - | |
03 | 2.8114: Change rate schedules or other changes in utility service | $17,784 | $500 |
$17,784
-
kWh
|
- | - | - | - | |
04 | 2.4226: Use / purchase optimum sized compressor | $9,933 | $34,000 |
$7,554
134,417
kWh
|
$2,379
-
kW-mo/yr
|
- | - | - | |
05 | 2.4226: Use / purchase optimum sized compressor | $3,805 | $10,500 |
$205
3,645
kWh
|
$3,600
-
kW-mo/yr
|
- | - | - | |
06 | 2.2437: Recover waste heat from equipment | $3,968 | $5,000 | - | - |
$3,968
-
MMBtu
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,126 | $200 |
$1,388
24,703
kWh
|
$438
-
kW-mo/yr
|
- | $(-300.0) | $(-400.0) | |
08 | 2.2612: Use cooling tower water instead of refrigeration | $4,233 | $20,700 |
$4,233
75,317
kWh
|
- | - | - | - | |
09 | 2.2511: Insulate bare equipment | $764 | $431 | - | - |
$764
-
MMBtu
|
- | - | |
10 | 2.7111: Reduce illumination to minimum necessary levels | $288 | $70 |
$136
2,420
kWh
|
$129
-
kW-mo/yr
|
- | - | $23 | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,001 | $26,800 |
$6,733
119,796
kWh
|
$2,120
-
kW-mo/yr
|
- | - | $1,148 | |
12 | 2.7135: Install occupancy sensors | $1,394 | $521 |
$1,394
24,792
kWh
|
- | - | - | - | |
13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,483 | $19,695 |
$2,499
44,460
kWh
|
$787
-
kW-mo/yr
|
- | - | $1,197 | |
14 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,028 | $6,967 |
$1,155
20,544
kWh
|
$533
-
kW-mo/yr
|
- | - | $340 | |
15 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $547 | $1,540 |
$452
8,042
kWh
|
- | - | - | $95 | |
16 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $710 | $192 |
$288
5,130
kWh
|
$63
-
kW-mo/yr
|
- | - | $359 | |
17 | 2.7134: Use photocell controls | $93 | $200 |
$93
1,650
kWh
|
- | - | - | - | |
18 | 2.4151: Develop a repair/replace policy | $2,232 | $4,256 |
$1,698
30,214
kWh
|
$534
-
kW-mo/yr
|
- | - | - | |
19 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,859 | $230 |
$1,414
25,154
kWh
|
$445
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $74,209 | $152,252 |
$47,068
521,034
kWh
|
$11,294
-
kW-mo/yr
|
$13,385
-
MMBtu
|
$(-300.0) | $2,762 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs