| Assessment Year | 1989 |
|---|---|
| Principal Product | REFUSE COLLECTION BODIES |
| NAICS |
n/a
|
| SIC | 3713: Truck and Bus Bodies |
| Sales Range | $5 M to 10M |
| # of Employees | 88 |
| Plant Area |
n/a
|
| Annual Production | 540
pieces
|
| Production Hrs. Annual | 4,335
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $55,071 | 1,072,978 |
kWh
|
$0.051 |
| Fuel Oil #2 | $20,743 | 5,460 |
MMBtu
|
$3.80 |
| Other Energy | $1,221 | 183 |
MMBtu
|
$6.67 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,126 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,922 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Other Energy Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $5,046 | - |
$594
11,430
kWh
|
$4,452
-
MMBtu
|
- | |
| 02 | 2.6124: Establish equipment maintenance schedule | $1,484 | $3,200 | - |
$1,484
-
MMBtu
|
- | |
| 03 | 2.7243: Improve air circulation with destratification fans / other methods | $1,204 | $4,800 | - |
$1,204
-
MMBtu
|
- | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $991 | - |
$991
19,050
kWh
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $777 | $270 |
$777
14,947
kWh
|
- | - | |
| 06 | 2.4312: Improve lubrication practices | $274 | - |
$274
5,275
kWh
|
- | - | |
| 07 | 2.6125: Keep equipment clean | $121 | $450 | - | - |
$121
-
MMBtu
|
|
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $229 | $261 |
$229
4,396
kWh
|
- | - | |
| TOTAL RECOMMENDED | $10,126 | $8,981 |
$2,865
55,098
kWh
|
$7,140
-
MMBtu
|
$121
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $8,922 | $4,181 |
$2,865
55,098
kWh
|
$5,936
-
MMBtu
|
$121
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Other Energy Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs