Assessment Year | 2015 |
---|---|
Principal Product | Furniture |
NAICS | 337121: Upholstered Household Furniture Manufacturing |
SIC | 2512: Wood Household Furniture, Upholstered |
Sales Range | $10 M to 50M |
# of Employees | 89 |
Plant Area |
450,000
ft2
|
Annual Production | 300,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $76,652 | 1,271,845 |
kWh
|
$0.060 |
Electricity Demand | $51,381 | 4,173 |
kW-mo/yr
|
$12.31 |
Coal | $31,330 | 6,266 |
MMBtu
|
$5.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $42,703 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,096 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Coal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $30,643 | $25,887 |
$11,781
195,146
kWh
|
$14,549
-
kW-mo/yr
|
- | - | - | $4,313 | |
02 | 2.7135: Install occupancy sensors | $1,207 | $944 |
$1,207
20,462
kWh
|
- | - | - | - | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $823 | $182 |
$342
5,800
kWh
|
$391
-
kW-mo/yr
|
- | - | - | $90 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $191 | $48 |
$78
1,281
kWh
|
$23
-
kW-mo/yr
|
- | - | - | $90 | |
05 | 2.7134: Use photocell controls | $4,235 | $600 |
$1,196
19,640
kWh
|
$3,039
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $692 | $503 |
$319
5,400
kWh
|
$363
-
kW-mo/yr
|
- | - | $10 | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $325 | $100 |
$213
3,492
kWh
|
$272
-
kW-mo/yr
|
- | $(-100.0) | - | $(-60.0) | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,094 | $1,000 |
$481
7,880
kWh
|
$613
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.4226: Use / purchase optimum sized compressor | $2,071 | $4,500 |
$64
1,084
kWh
|
$2,007
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.4239: Eliminate or reduce compressed air usage | $33 | $150 |
$33
546
kWh
|
- | - | - | - | - | |
11 | 2.2135: Repair and eliminate steam leaks | $311 | $200 | - | - |
$311
-
MMBtu
|
- | - | - | |
12 | 2.4151: Develop a repair/replace policy | $1,078 | $3,411 |
$503
8,532
kWh
|
$575
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $42,703 | $37,525 |
$16,217
269,263
kWh
|
$21,832
-
kW-mo/yr
|
$311
-
MMBtu
|
$(-100.0) | $10 | $4,433 | ||
TOTAL IMPLEMENTED | $34,096 | $30,481 |
$13,269
220,197
kWh
|
$16,173
-
kW-mo/yr
|
$311
-
MMBtu
|
$(-100.0) | $10 | $4,433 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Coal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs